Planning performance agreement
Planning performance agreements are voluntary undertakings that enable local planning authorities and applicants for planning permission to agree the timescales, actions and resources necessary to process a planning application. They are not intended to be legally-binding contracts, but are in the spirit of a ‘memorandum of understanding’.
They must be agreed before an application is submitted, and can cover the pre-application, application and post-application stages.
Planning performance agreements can be helpful in:
- Encouraging collaborative working between the applicant, the local planning authority, and third parties (where appropriate, third parties such as statutory consultees may be a party to the agreement).
- Establishing a transparent process for determining applications.
- Acting as focus for pre-application discussions.
They can be used for any application, but are particularly suited to large or complex applications. The structure of the agreement is determined by the local planning authority and the applicant, but depending on the complexity of the project may include:
- The status of the agreement.
- A shared vision.
- An agreed timetable.
- Development objectives.
- Responsibility for tasks.
- A programme for the negotiation of section 106 agreements and related non-planning consents.
- Voluntary payments to assist with any abnormal costs associated with processing the application.
Local planning authorities may charge for additional administrative work involved in the planning performance agreement.
The existence of a planning performance agreement means that the statutory time limits for determining the application no longer apply. If the local planning authority fails to determine the application by the agreed date, then the applicant may appeal, however, the agreement should be sufficiently flexible to allow for changes in circumstances.
The parties to the agreement are encouraged to make it publicly available.
[edit] Related articles on Designing Buildings Wiki
- Detailed planning application.
- Development management.
- Environmental impact assessment.
- National Planning Policy Framework.
- National Planning Practice Guidance.
- Neighbourhood planning.
- Outline planning application.
- Permitted development.
- Planning appeal.
- Planning authority.
- Planning conditions.
- Planning enforcement.
- Planning fees.
- Planning objection.
- Planning obligations.
- Planning permission.
- Pre-application advice.
- Section 106 agreement.
- Statutory consultees.
Featured articles and news
Costs and insolvencies mount for SMEs, despite growth
Construction sector under insolvency and wage bill pressure in part linked to National Insurance, says report.
The place for vitrified clay pipes in modern infrastructure
Why vitrified clay pipes are reclaiming their role in built projects.
Research by construction PR consultancy LMC published.
Roles and responsibilities of domestic clients
ACA Safety in Construction guide for domestic clients.
Fire door compliance in UK commercial buildings
Architect and manufacturer gives their low down.
Plumbing and heating for sustainability in new properties
Technical Engineer runs through changes in regulations, innovations in materials, and product systems.
Awareness of the Carbon Border Adjustment Mechanism
What CBAM is and what to do about it.
The new towns and strategic environmental assessments
12 locations of the New Towns Taskforce reduced to 7 within the new towns draft programme and open consultation.
Buildings that changed the future of architecture. Book review.
The Sustainability Pathfinder© Handbook
Built environment agency launches free Pathfinder© tool to help businesses progress sustainability strategies.
Government outcome to the late payment consultation, ECA reacts.
IHBC 2025 Gus Astley Student Award winners
Work on the role of hewing in UK historic conservation a win for Jack Parker of Oxford Brookes University.
Future Homes Building Standards and plug-in solar
Parts F and L amendments, the availability of solar panels and industry responses.
How later living housing can help solve the housing crisis
Unlocking homes, unlocking lives.
Preparing safety case reports for HRBs under the BSA
A new practical guide to preparing structural inputs for safety cases and safety case reports published by IStructE.
Male construction workers and prostate cancer
CIOB and Prostate Cancer UK encourage awareness of prostate cancer risks, and what to do about it.