Contingencies in construction
Contingencies are downside risk estimates that make allowance for the unknown risks associated with a project.
Typically, contingencies refer to costs, and are amounts that are held in reserve to deal with unforeseen circumstances. However, they may also refer to other aspects of the project, for example, the programme may include a contingency where it is important that a specific completion date is achieved.
A contingency may also refer to part of a contingency plan, which is a plan that can be enacted to mitigate project risks, such as adverse weather, an industrial dispute, supplier failure, and so on.
Monetary contingencies are typically referred to in relation to the overall client for a project. However, other parties in the supply chain are also likely to include contingencies in their cost planning.
While it is advisable for clients to hold a contingency, they might no wish to share this information with the rest of the project team, who may see a contingency as a license to exceed the budget in the knowledge that the client has a reserve that can be spent.
Contingencies are often expressed in terms of percentages. The percentage contingencies applied are at their greatest in the early stages of the project when there are the greatest number of possible risks. But they can then be reduced as better particulars about the project become available and some risks have passed or been overcome.
An example of how a contingency might be reduced during a project is set out below:
- At the preliminary business plan stage, total cost estimates might include a 15% contingency.
- In the elemental cost plan this might reduce to 10% of fees and construction costs.
- On awarding the contract, 5% of the contract value might be included as contingency in the cost plan.
In addition to a contingency, the client is likely to hold retention. Retention is a percentage (often 5%) of the amount certified as due to the contractor on an interim certificate, that is deducted from the amount due and retained by the client. The purpose of retention is to ensure that the contractor properly completes the activities required of them under the contract. Retention can also be applied to nominated sub-contractors, and the main contractor may also apply retention to domestic sub-contractors.
[edit] Related articles on Designing Buildings
Featured articles and news
Boiler Upgrade Scheme and certifications consultation
Summary of government consultation which closes 11 June 2025.
Deputy editor of AT, Tim Fraser, discusses the newly formed society with its current chair, Chris Halligan MCIAT.
Barratt Lo-E passivhaus standard homes planned enmasse
With an initial 728 Lo-E homes across two sites and many more planned for the future.
Government urged to uphold Warm Homes commitment
ECA and industry bodies write to Government concerning its 13.2 billion Warm Homes manifesto commitment.
Places of Worship in Britain and Ireland, 1929-1990. Book review.
The emancipation of women in art.
CIOB Construction Manager of the Year 2025
Just one of the winners at the CIOB Awards 2025.
Call for independent National Grenfell oversight mechanism
MHCLG share findings of Building Safety Inquiry in letter to Secretary of State and Minister for Building Safety.
The Architectural Technology Awards
AT Awards now open for this the sixth decade of CIAT.
50th Golden anniversary ECA Edmundson awards
Deadline for submissions Friday 30 May 2025.
The benefits of precast, off-site foundation systems
Top ten benefits of this notable innovation.
Encouraging individuals to take action saving water at home, work, and in their communities.
Takes a community to support mental health and wellbeing
The why of becoming a Mental Health Instructor explained.
Mental health awareness week 13-18 May
The theme is communities, they can provide a sense of belonging, safety, support in hard times, and a sense purpose.
Mental health support on the rise but workers still struggling
CIOB Understanding Mental Health in the Built Environment 2025 shows.
Design and construction material libraries
Material, sample, product or detail libraries a key component of any architectural design practice.
Construction Products Reform Green Paper and Consultation
Still time to respond as consultation closes on 21 May 2025.
Resilient façade systems for smog reduction in Shanghai
A technical approach using computer simulation and analysis of solar radiation, wind patterns, and ventilation.