Pirelli General Cable Works Ltd v Oscar Faber & Partners
The case of Pirelli General Cable Works Ltd v Oscar Faber & Partners [1983] has been used as precedent for the limitation period applicable to claims of negligent design.
Damage to a factory arose out of the use of a material in constructing a factory chimney that was unsuitable for the purpose. The chimney had been built in 1969 but the faulty condition of the chimney could not have been discovered with reasonable diligence until 1972 and was not in fact discovered until 1977. A writ was issued in 1978. The question was whether the six year period ran from the date the faulty chimney was built or from the date when the fault could have been or was discovered. |
https://publications.parliament.uk/pa/ld200506/ldjudgmt/jd060301/haward-2.htm |
The House of Lords held that the owner of a building had a legitimate cause of action against the consulting engineer for a negligent design at the point at which physical damage to the building first occurred.
The subsequent case of Abbott v Will Gannon & Smith Ltd [2005] challenged the Pirelli law at the Court of Appeal on the basis that the case of Murphy v Brentwood DC [1991] decided that the cause of action accrued, not when physical damage first occurred but when the building owner suffered economic loss.
The Court held that the Murphy decision had not expressly or impliedly overruled the Pirelli decision. It held that if the claimant’s cause of action accrued at the time they suffered economic loss, then the loss only occurred when it became apparent in some way which would affect the building’s value. Therefore, they rejected the argument that economic loss was suffered when negligent works were completed.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
The role of construction in tackling the biodiversity crisis
New CIOB Nature of Building digital series available now.
The Nature Towns and Cities initiative
Grants of up to 1 million for local councils and partners.
The continued ISG fall out October updates
Where to look for answers to frequently asked questions.
Building safety remediation programme for Wales
With 2024 October progress updates.
In major support package for small businesses.
Conservation and transformation
Reading Ruskin’s cultural heritage. Book review.
Renovating Union Chain Bridge.
AI tools for planning, design, construction and management
A long, continually expanding list, any more to add?
Robots in the construction industry
From cultural characterisations to construction sites.
Empowering construction with AI integration
New horizons with a human touch.
Key AI related terms to be aware of
With explanations from the UK government.
A Better Hiring Toolkit for construction
Tooling up to hire under best practice standards in the sector.
Recharging Electrical Skills in Wales
Step by step collaborative solutions.
Ireland budget announcement 2025
CIOB responds with positivity, criticism and clarity.
New HES national centre for traditional building retrofit
Announced as HES publishes survey results which reveal strong support for retrofit.
Retrofit of Buildings, a CIOB Technical Publication
Expected to become one of the largest activities in the global construction industry.