Ampurius Nu Homes Holdings Ltd v Telford Homes (Creekside) Ltd (2012) EWHC 1820
[edit] High Court (Chancery Division) (England and Wales) 2012
The claimant and the defendant (a construction company) entered into a contract for the construction and grant of long leases on a development scheme for which the defendant acquired the freehold. The defendant was required under the contract to proceed with 'due diligence' and to 'use reasonable endeavours' to complete the works by the target date. However, the defendant ran into financial difficulties ceased work.
The claimant alleged that this was a repudiatory breach, but did not terminate the contract for 11 months. It was the defendant who repudiated the contract.
Judgment was given in favour of the claimant.
In so doing, The court held that the defendant was in breach of the term of the contract requiring due diligence by failing to carry out the works assiduously or expeditiously. It was also held that although the breach may not have been repudiatory at the outset, it could become so over time if it deprived the innocent party of the benefit of a significant part of the contract. Negotiation over the course of the breach did not mean the claimant had affirmed the contract.
[edit] Court of Appeal (Civil Division) (England and Wales) 2013
In 2013 this decision was overturned by the Court of Appeal. It was not disputed that Telford had been in breach of contract, but the court held that an 18 month delay on a 999-year lease was not sufficient to constitute a repudiatory breach (a breach that it indicates one party no longer intends to accept its obligations under the contract, allowing the innocent party to terminate the contract and to sue for damages) and so did not entitle Ampurius to terminate the contract.
[edit] External references
Featured articles and news
Councils and communities highlighted for delivery of common-sense housing
As government follows up with mandatory housing targets.
CIOB photographic competition final images revealed
Art of Building produces stunning images for another year.
HSE prosecutes company for putting workers at risk
Roofing company fined and its director sentenced.
Strategic restructure to transform industry competence
EBSSA becomes part of a new industry competence structure.
Major overhaul of planning committees proposed by government
Planning decisions set to be fast-tracked to tackle the housing crisis.
Industry Competence Steering Group restructure
ICSG transitions to the Industry Competence Committee (ICC) under the Building Safety Regulator (BSR).
Principal Contractor Competency Certification Scheme
CIOB PCCCS competence framework for Principal Contractors.
The CIAT Principal Designer register
Issues explained via a series of FAQs.
Conservation in the age of the fourth (digital) industrial revolution.
Shaping the future of heritage
Embracing the evolution of economic thinking.
Ministers to unleash biggest building boom in half a century
50 major infrastructure projects, 5 billion for housing and 1.5 million homes.
RIBA Principal Designer Practice Note published
With key descriptions, best practice examples and FAQs, with supporting template resources.
Electrical businesses brace for project delays in 2025
BEB survey reveals over half worried about impact of delays.
Accelerating the remediation of buildings with unsafe cladding in England
The government publishes its Remediation Acceleration Plan.
Airtightness in raised access plenum floors
New testing guidance from BSRIA out now.
Picking up the hard hat on site or not
Common factors preventing workers using head protection and how to solve them.