Self-build home: Confirm appointment of the design and build contractor to construct the home
NB Where a single-stage procurement route has been followed, and the contractor’s initial appointment was for both design and construction, the contract sum for the construction of the home will already have been agreed.
Ideally, when the the design and build contractor's appointment to construct the home is confirmed, negotiation is a mathematical exercise following the pricing criteria agreed in the first-stage when the contractor was appointed to design the home.
The first-stage appointment might have been made on the basis of a bespoke agreement, a consultancy agreement or a pre-construction services agreement (PCSA), with an appendix setting out the tender items to be applied to the construction contract, with a clause that made it clear there is no obligation to proceed to the construction contract, and in such circumstances the pre-construction fee would be full and final settlement of the contractor's costs.
However, there are likely to be items not anticipated in the first stage, for which negotiations will be necessary.
Negotiating at this point is difficult because the contractor is ‘embedded’ in the project and there is little threat from competition. This can mean that tender prices for the second stage of two-stage contracts are higher than traditional contracts, which are subject to full competition. However, there tend to be fewer variations and fewer claims; as the contractor has a longer period of familiarity with the project and a better-developed relationship with the self builder.
Ideally there will be some means of securing an alternative bid if negotiations with the contractor fail, albeit this is likely to result in delays and difficulties in attributing design liability.
Featured articles and news
How to revolutionise UK housing with MMC
CIC and Supply Chain Sustainability School unveil a plan.
From the UKs largest manufacturer and supplier of lime.
From mud bricks to smart concrete
A brief history from 7000BC to a future on the moon.
Regulator of Social Housing publishes latest fire safety report
Covering remediation of 11 metre plus social housing sector buildings.
Apartment and Duplex Defects Remediation Bill 2024
Approved for priority drafting by Government of Ireland.
The long list with in the frame of key historical events.
Competence frameworks for sustainability in the built environment
Code of practice, core criteria consultation draft for comment.
UK Net Zero Carbon Buildings Standard Sept update
Pilot version for testing and feedback on its adoption due.
New Floods Resilience Taskforce
With a wet met office autumn prediction.
National Retrofit Hub takeover of Net Zero stage
At Birmingham UK Construction Week in October.
AT Awards 2024 finalists announced
With more to come, prior to the Awards ceremony in October.
London construction cools as hotspots appear nationally
Increases in the East of England, Yorkshire and Scotland.
ARB proposals for a new Architects Code
Announced in the shadow of the final Grenfell Inquiry report.
Combining human creativity and tech innovation now and in the future
Building automation and control systems market study
BSRIA 2024 North America BACS software & services.
Impact of digital technology on productivity in construction
New CIOB academy guidance for companies of all sizes.