Payment notice for construction contracts
I have a question:
Say a contractor has issued their valuation, the employer has issued their assessment on the valuation and passed it back to the contractor who has ignored the assessment and not passed comment or acceptance despite chasing from the employer. The five days passes on this day and the following day, the payment notice is issued based on the Employer's Assessment.
Is this acceptable under JCT D&B 2016 contract?
Thanks,
QS
Good information and helpful.
Quick question I have relating to a subcontractor's payment application received. I made an assessment and issued to the subcontractor in error. This was then later revised and payment was made on the revised assessment. How does this stand in terms of final account?
Thanks,
Michael
My gut feeling is that you are entitled to revise an assessment up or down at any time prior to agreeing a final account providing you can support the revision with tangible evidence such as a mathematical or quantification error. Any element of subjective judgment however is more tricky, as a downward adjustment might be interpreted as a negotiating tactic or client pressure.
Clearly the precise answer will depend on the terms of the relevant sub-contract and any terms attached to the valuation...written or oral. But as a general rule interim valuations are just that and can be revised up or down before the final certificate or any binding agreement on any final account. Also it is a general principle of law that mistakes of fact can be amended or may not even be binding as the law recognizes a defence of mistake of fact though not mistake of law and provided no estoppel has arisen.
Hi i am a quantity surveying uni student and i need to write a paper on payments in the construction industry. Is the interim valuation submitted by the contractor and then is valued and certified by the officers in charged OR do the officers in charged just make an interim valuation every month when the time comes??
Thanks.
So, if you owe a company and plan to pay them on 15th of the month and issue a payless on 13th of that same month, is this in order and correct or has it to be no less than 5 days beforehand?
Hi, I have a situation where a payment has been missed. The Contractor has not issued a default payment notice. If her has not issued a formal notice does the Client still have to pay the contractor his stated amount due in his original valuation submission?
In calculating his payment due in his valuation submission he has made an arithmetic error by deducting too much retention. Is his amount due the net amount at the end of the calculation or the gross valuation amount?
I have a question
If I issue an application and the contractor issues a payment notice that is less than the sum applied for does the contractor have to issue a payless notice?
Thanks
You must sign in or register to edit or comment on an article
Featured articles and news
RTPI leader to become new CIOB Chief Executive Officer
Dr Victoria Hills MRTPI, FICE to take over after Caroline Gumble’s departure.
Social and affordable housing, a long term plan for delivery
The “Delivering a Decade of Renewal for Social and Affordable Housing” strategy sets out future path.
A change to adoptive architecture
Effects of global weather warming on architectural detailing, material choice and human interaction.
The proposed publicly owned and backed subsidiary of Homes England, to facilitate new homes.
How big is the problem and what can we do to mitigate the effects?
Overheating guidance and tools for building designers
A number of cool guides to help with the heat.
The UK's Modern Industrial Strategy: A 10 year plan
Previous consultation criticism, current key elements and general support with some persisting reservations.
Building Safety Regulator reforms
New roles, new staff and a new fast track service pave the way for a single construction regulator.
Architectural Technologist CPDs and Communications
CIAT CPD… and how you can do it!
Cooling centres and cool spaces
Managing extreme heat in cities by directing the public to places for heat stress relief and water sources.
Winter gardens: A brief history and warm variations
Extending the season with glass in different forms and terms.
Restoring Great Yarmouth's Winter Gardens
Transforming one of the least sustainable constructions imaginable.
Construction Skills Mission Board launch sector drive
Newly formed government and industry collaboration set strategy for recruiting an additional 100,000 construction workers a year.
New Architects Code comes into effect in September 2025
ARB Architects Code of Conduct and Practice available with ongoing consultation regarding guidance.
Welsh Skills Body (Medr) launches ambitious plan
The new skills body brings together funding and regulation of tertiary education and research for the devolved nation.
Paul Gandy FCIOB announced as next CIOB President
Former Tilbury Douglas CEO takes helm.
UK Infrastructure: A 10 Year Strategy. In brief with reactions
With the National Infrastructure and Service Transformation Authority (NISTA).