Contingency plan
Contingency plans are plans than could be enacted to mitigate project risks identified during risk assessment, if those risks increase or materialise. That is, they are alternative courses of action devised to cope with project risks.
Predictable risks that could be mitigated with forward planning might include:
- Non-delivery of materials. An alternative design might be prepared, or bulk or specific items could be pre-ordered before contractors are appointed
- Lack of available work force. This could be tackled by the provision of a site labour camp or by overseas recruitment.
- Lack of plant and equipment availability (or plant failure or access to spare parts). Plant such as piling rigs and spares could be ordered during the design stages prior to contractor involvement.
- Illness. This could be mitigated by insurance cover for key personnel.
- The risk of obtaining planning permission or other statutory approvals. This might be mitigated by early consultation with statutory authorities prior to design, or by employing ex-statutory authority employees, or consultants familiar with the statutory authority.
- Information and communications technology failure. This might be mitigated by duplicating facilities, establishing back-up procedures and providing uninterrupted power supplies.
- Failure of power or water supply. This might be mitigated by the duplication of supply, uninterrupted power supplies or the provision of standby generators.
NB Functional Standards Common Glossary, published by the Cabinet Office, defines contingency planning/ plans as: ‘A course of action and resulting document(s) that prepares the organisation to respond effectively to future significant events, incidents and risks.’
[edit] Related articles on Designing Buildings
Featured articles and news
How to revolutionise UK housing with MMC
CIC and Supply Chain Sustainability School unveil a plan.
From the UKs largest manufacturer and supplier of lime.
From mud bricks to smart concrete
A brief history from 7000BC to a future on the moon.
Regulator of Social Housing publishes latest fire safety report
Covering remediation of 11 metre plus social housing sector buildings.
Apartment and Duplex Defects Remediation Bill 2024
Approved for priority drafting by Government of Ireland.
The long list with in the frame of key historical events.
Competence frameworks for sustainability in the built environment
Code of practice, core criteria consultation draft for comment.
UK Net Zero Carbon Buildings Standard Sept update
Pilot version for testing and feedback on its adoption due.
New Floods Resilience Taskforce
With a wet met office autumn prediction.
National Retrofit Hub takeover of Net Zero stage
At Birmingham UK Construction Week in October.
AT Awards 2024 finalists announced
With more to come, prior to the Awards ceremony in October.
London construction cools as hotspots appear nationally
Increases in the East of England, Yorkshire and Scotland.
ARB proposals for a new Architects Code
Announced in the shadow of the final Grenfell Inquiry report.
Combining human creativity and tech innovation now and in the future
Building automation and control systems market study
BSRIA 2024 North America BACS software & services.
Impact of digital technology on productivity in construction
New CIOB academy guidance for companies of all sizes.
Comments
[edit] To make a comment about this article, or to suggest changes, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.