Abortive work in building design and construction
Abortive work (or abortive costs or abortive fees) refers to work that has been started or carried out, but is not needed, or is no longer needed, and will not form part of the final development. The work will be wasted.
Abortive work can occur at any stage of a project, relating to the tender process, the work of consultants or construction.
Abortive work can arise because of:
- Cancellation of a project or an element of a project.
- Failed or abortive tendering.
- A change of circumstances (for example a change in legislative requirements).
- Clarification of circumstances (for example the opening up of existing works, or below ground works).
- Refusal of planning permission or other approvals.
- Changes in requirements, such as budget, location, size and technical requirements.
- The work carried out was unauthorised.
- The work was not properly authorised.
- Mistakes or misunderstandings.
- Clashes resulting from poor co-ordination.
- Design changes during manufacture or construction.
- Changes required once the completed works have been seen.
- Procurement of redundant goods, materials, plant or personnel.
The occurrence of abortive work can be reduced by:
- Undertaking thorough site investigations and condition surveys.
- Ensuring that the project brief is comprehensive and is supported by all stakeholders (including end users).
- Ensuring that legislative requirements are properly integrated into the project.
- Ensuring that risks are properly identified.
- Introducing change-control procedures at key stages, with progressive gateways at which the project is defined, agreed, a decision taken to proceed to the next stage and some aspects frozen.
- Applying for permissions as early as is practicable.
- Ensuring designs are properly co-ordinated before tender.
- Limiting the number of tenderers and the extent of the tender process (particularly for procurement routes such as the private finance initiative, or prime contracting for which tender costs can be very high) .
- Only tendering for work where the chance of success is high.
- Adopting quality assurance systems.
- Adopting assistive technologies such as building information modelling (BIM) to improve co-ordination.
- Frequent site inspections.
- Suspending the works while potential changes are assessed in order to minimise potential abortive works.
Where abortive work is carried out, the cost of those works will be allocated depending on the wording of the contract.
Very broadly, the costs may be borne by the client if the conditions set out in the contract have been met (sometimes referred to as abortive terms), if the client has accepted the risk for unknown items (such as ground conditions) or if there has been a breach of contract by the client.
Where a change has been instructed by the client in accordance with the contract that might result in abortive work, this may give rise to additions or deductions from the contract sum and may also (but not necessarily) require adjustment of the completion date.
Where the consultant or contractor has carried out unauthorised or non-compliant work, or they have accepted the risk for unknown items, they may bear the cost of abortive work.
[edit] Related articles on Designing Buildings Wiki
- Change control procedure
- Cost control.
- Remedial work.
- Scope creep.
- Variation.
- Value engineering.
- Value management.
[edit] External references
Featured articles and news
From the UKs largest manufacturer and supplier of lime.
From mud bricks to smart concrete
A brief history from 7000BC to a future on the moon.
Regulator of Social Housing publishes latest fire safety report
Covering remediation of 11 metre plus social housing sector buildings.
Apartment and Duplex Defects Remediation Bill 2024
Approved for priority drafting by Government of Ireland.
The long list with in the frame of key historical events.
Competence frameworks for sustainability in the built environment
Code of practice, core criteria consultation draft for comment.
UK Net Zero Carbon Buildings Standard Sept update
Pilot version for testing and feedback on its adoption due.
New Floods Resilience Taskforce
With a wet met office autumn prediction.
National Retrofit Hub takeover of Net Zero stage
At Birmingham UK Construction Week in October.
AT Awards 2024 finalists announced
With more to come, prior to the Awards ceremony in October.
London construction cools as hotspots appear nationally
Increases in the East of England, Yorkshire and Scotland.
ARB proposals for a new Architects Code
Announced in the shadow of the final Grenfell Inquiry report.
Combining human creativity and tech innovation now and in the future
Building automation and control systems market study
BSRIA 2024 North America BACS software & services.
Impact of digital technology on productivity in construction
New CIOB academy guidance for companies of all sizes.
Demolition and retrofit approaches in Planning Policy
MHCLG demolition and retrofit survey to inform future updates to national planning policy.
Expert taskforce to spearhead new, new town generation
Sir Michael Lyons given 12 months for recommendations.
Government policy statement on new towns
A coded vision for a new generation of new towns.
Comments