Underreaming
Underreaming is a process used to widen the foot of a bored hole or foundation pier so as to increase its loadbearing area.
It is generally undertaken for safety and/or efficiency reasons, or because of restrictions in the ground, that prevent the use of a pier or pile that is wider along its entire length, and is most common on offshore drilling operations, exploration wells, extended reach drilling, and so on.
Underreaming may also be carried out to create tension piles, where the widened foot resists uplift forces that might otherwise cause the pile to be extracted from the ground. For more information see: Tension pile.
It can also be used in the formation of ground anchors.
Typically, the process involves a drill pipe with cutter blades that can be forced open by pumping a fluid into the pipe. The underreaming tool is kept open by the drilling weight and hydraulics from the pump pressure. The pumps are disengaged when the desired depth has been reached. The underreamer closes and is pulled out of the hole.
It may be necessary to use water flushing systems to remove the reamed spoil from the hole and grout to maintain the integrity of the underream.
There is the risk that if the underreamer is left in the hole for too long, the amount of material left in the hole increases. Also, if penetration rates are too high, this can result in a corkscrewed, under-gauged hole.
It is possible to drill a pilot hole and then underream, or to drill and underream as part of the the same drilling operation.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Permitted development rights for agricultural buildings
The changes coming into effect as of May 21, 2024.
Biodiversity and the built environment digital series
The nature of building, with CIOB and CWP.
A call for prevention and sensitive re-use.
Risks to the long-term effectiveness of the BNG scheme
National Audit Office publish review of Biodiversity Net Gain.
The CIAT principal designer register
Providing assurance and verification of the capability and competence of registered ATs.
Building Safety recommendations and Northern Ireland
The NI roadmap to improving safety in high rise residential.
Specifying rendered external wall insulation for fire safety
How to interrogate the evidence provided to the specifier.
The benefits of writing articles for your organisation
How to create a profile for your organisation and publish for free.
No Falls Week. The importance of safe working at height
What to expect and what is on offer to avoid accidents.
Scottish Government action to reach net-zero targets
Retrofit expert group highlight critical actions needed.
A forward thinking, inclusive global community of members.
From engineered product life-spans, to their extension.
Circular economy in the built environment
A brief description from 2021. Where are we now?
CLC publishes domestic retrofit competency framework
Roadmap of Skills for net zero.
Understanding is key to conservation.
Open industry engagement survey seeks responses
Institutions and the importance of engagement.