Alcatel period
Contents |
[edit] Overview
Public contracting authorities must leave a period of least 10 days between a contract award decision and the formal award of the contract. This is known as the standstill (Alcatel) period. It is a legal requirement for all public contracting authority procurement processes covered by the full scope of the EU Procurement Directives.
The purpose of the standstill is to allow unsuccessful bidders the chance to obtain more information on the award of the contract so they can take appropriate action if they believe they have been unfairly treated.
The term 'Alcatel period' derives from two European cases (C81/98 - Alcatel Austria v Bundeministerium für Wissenschaft und Verkehr and C212/02 - Commission v Austria) which brought about the change in the law.
[edit] What does it apply to?
The period applies to ‘public contracting authorities’ for the supply of goods, works and services contracts above the threshold value. These thresholds range from around £156,000 for essential local government supplies and services contacts (£101,000 for central government) up to around £3,927,000 for works contracts. Similar regulations apply to utilities companies.
[edit] Beginning of the standstill period
The commencement of the standstill (Alcatel) period is from the date the authority decides to award the contract. At this point, the authority will produce an Alcatel letter indicating the beginning of the standstill. This provides bidders with the opportunity to challenge the award decision before the contracts are signed.
[edit] Duration of standstill
The standstill (Alcatel) period will last from 10 to 15 days, depending on the method by which the Alcatel letter is communicated.
It is usual that if the means of communication is electronic, that the time period will be 10 days. However, if the means is to be non-electronic then this can be either 15 days from the date of sending, or 10 days from the date of receipt.
[edit] Legal background
The Public Contracts Regulations 2006 implement into law the European Commission’s Directive on public procurement (2004/18/EC).
[edit] Timeline
The 10-day period is usually scheduled as follows:
- Day 0: Notification of award decision through the Alcatel letters.
- Day 2: Deadline for unsuccessful bidders to request an ‘accelerated debrief’. This can be a means of obtaining information that may facilitate a challenge to the award.
- Day 3 to 7: Responses must be made to debriefing requests during this period. Should there be delays in providing the necessary information the standstill period can be extended.
- Day 10: Standstill period ends at midnight.
- Day 11: If no legal challenge is brought forward, the final award of the contract is made.
In 2009, the provision for an accelerated debrief changed, with the necessary details relating to the contract award decision needing to be provided to all unsuccessful bidders without them having to request it by the end of Day 2.
For more information, see Accelerated debrief.
[edit] Related articles on Designing Buildings Wiki.
- Accelerated debrief.
- Breach of contract.
- Construction contract.
- Contract award.
- Contract conditions.
- Contract documents.
- Contract v tort.
- Contracts under seal v under hand.
- Essentials of a contract.
- Framework contract.
- Government Construction Strategy.
- Letter of award.
- OJEU procurement practices.
- PFI.
- Procurement route.
- Public procurement.
- Social value act.
- Sub-contract.
- Tender documentation.
- Tender processes.
[edit] External references
- Public Contracts Regulations 2006.
- Directive on public procurement (2004/18/EC).
Featured articles and news
Regulator of Social Housing publishes latest fire safety report
Covering remediation of 11 metre plus social housing sector buildings.
Apartment and Duplex Defects Remediation Bill 2024
Approved for priority drafting by Government of Ireland.
The long list with in the frame of key historical events.
Competence frameworks for sustainability in the built environment
Code of practice, core criteria consultation draft for comment.
UK Net Zero Carbon Buildings Standard Sept update
Pilot version for testing and feedback on its adoption due.
New Floods Resilience Taskforce
With a wet met office autumn prediction.
National Retrofit Hub takeover of Net Zero stage
At Birmingham UK Construction Week in October.
AT Awards 2024 finalists announced
With more to come, prior to the Awards ceremony in October.
London construction cools as hotspots appear nationally
Increases in the East of England, Yorkshire and Scotland.
ARB proposals for a new Architects Code
Announced in the shadow of the final Grenfell Inquiry report.
Combining human creativity and tech innovation now and in the future
Building automation and control systems market study
BSRIA 2024 North America BACS software & services.
Impact of digital technology on productivity in construction
New CIOB academy guidance for companies of all sizes.
Demolition and retrofit approaches in Planning Policy
MHCLG demolition and retrofit survey to inform future updates to national planning policy.
Expert taskforce to spearhead new, new town generation
Sir Michael Lyons given 12 months for recommendations.
Government policy statement on new towns
A coded vision for a new generation of new towns.