Schedule of defects
A schedule of defects (or defects schedule) is issued by the contract administrator at the end of defects liability period. It identifies defects (aspects of the works that are not in accordance with the contract) that have become apparent during the defects liability period.
The contract administrator and the contractor then agree a reasonable period within which the contractor will rectify the defects identified on the schedule. Once the contract administrator is satisfied that the defects have been rectified, they issue a certificate of making good defects which has the effect of allowing the final certificate to be issued, releasing any remaining retention.
It is important to note that the defects liability period is not a chance to correct problems apparent at practical completion, it is a period during which the contractor may be recalled to rectify defects which appear. If there are defects apparent before practical completion, then these should be rectified before a certificate of practical completion is issued. See the article on practical completion for more information.
NB: Under NEC contracts, at, or just after the defects date the supervisor issues a defects certificate, which either certifies that there are no patent defects, or lists any uncorrected defects. This is analogous to the schedule of defects. See Defects certificate for more information.
[edit] Related articles on Designing Buildings
- Certificate of making good defects.
- Contract administrator.
- De minimis.
- Defects.
- Defects certificate.
- Defects liability period.
- Handover to client.
- Latent defects.
- Liquidated damages.
- Migration strategy.
- Opening up works for inspection and testing.
- Patent defects.
- Practical completion.
- Protecting and storing rebar.
- Punch list.
- Remedial work.
- Retention.
- Schedule.
- Schedule of condition.
- Site inspection.
- Soft landings.
- Substantial completion.
Featured articles and news
Ireland's National Residential Retrofit Plan
Staged initiatives introduced step by step.
Solar panels, pitched roofs and risk of fire spread
60% increase in solar panel fires prompts tests and installation warnings.
Modernising heat networks with Heat interface unit
Why HIUs hold the key to efficiency upgrades.
Reflecting on the work of the CIOB Academy
Looking back on 2025 and where it's going next.
Procurement in construction: Knowledge hub
Brief, overview, key articles and over 1000 more covering procurement.
Sir John Betjeman’s love of Victorian church architecture.
Exchange for Change for UK deposit return scheme
The UK Deposit Management Organisation established to deliver Deposit Return Scheme unveils trading name.
A guide to integrating heat pumps
As the Future Homes Standard approaches Future Homes Hub publishes hints and tips for Architects and Architectural Technologists.
BSR as a standalone body; statements, key roles, context
Statements from key figures in key and changing roles.
ECA launches Welsh Election Manifesto
ECA calls on political parties at 100 day milestone to the Senedd elections.
Resident engagement as the key to successful retrofits
Retrofit is about people, not just buildings, from early starts to beyond handover.
Plastic, recycling and its symbol
Student competition winning, M.C.Esher inspired Möbius strip design symbolising continuity within a finite entity.
Do you take the lead in a circular construction economy?
Help us develop and expand this wiki as a resource for academia and industry alike.
Warm Homes Plan Workforce Taskforce
Risks of undermining UK’s energy transition due to lack of electrotechnical industry representation, says ECA.
Cost Optimal Domestic Electrification CODE
Modelling retrofits only on costs that directly impact the consumer: upfront cost of equipment, energy costs and maintenance costs.
The Warm Homes Plan details released
What's new and what is not, with industry reactions.






















