Opening up works for inspection and testing
Construction contracts generally make provision for the contract administrator to instruct that inspections are carried out and that tests are undertaken on completed work where they suspect that there may be defects. They may carry out these tests themselves, or can have them carried out by third parties.
If those works have already been covered up, then this may require that they are opened up for inspection and testing, and clearly this may involve some cost and disruption for the contractor.
Where works are opened up, and tests reveal that there was no defect, then this may constitute a ‘relevant event’ and could entitle the contractor to an extension of time, and an addition may be made to the contract sum to pay the contractor’s costs, unless there was a requirement for the inspection or test to be carried out in the contract.
If a defect is revealed, the contractor must rectify it at their own cost.
Where a defect is revealed, and the contract administrator has reasonable cause to believe there may be other, similar defects (for example, a defect in the installation of insulation in one area may suggest there are similar defects elsewhere), they may issue further instructions for more of the works to be opened up. The contractor is not generally entitled to any adjustment of the contract sum or the completion date for these further tests, even if no further defects are found.
Similar provisions may exist in subcontracts allowing the contractor to instruct that subcontractors open up works for inspection and testing.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
- Building regulations inspection.
- Building sector failing on supervision.
- Certificate of making good defects.
- Decennial liability.
- Defects.
- Defects certificate.
- Defects correction period.
- Defects date.
- Defects liability period.
- Delay damages.
- Design liability.
- Desktop study.
- Dilapidations.
- Fit for purpose.
- Inspection.
- Latent defects.
- Patent defects.
- Practical completion.
- Remedial work.
- Scaffold register.
- Schedule of defects.
- Site inspector.
- Site inspection.
- Testing construction materials.
[edit] External references
- Out-law - Defective work in construction projects
- ‘The JCT 05 Standard Building Sub-contract’, BARNES, P., Blackwell Publishing (2006)
Featured articles and news
Not buildings. Happy holiday from DB.
Future Homes Standard: Industry calls for more ambition
As the Government FHS consultation finally closes.
Improving government projects with data and AI
Enabling better outcomes, efficient modern delivery and influential leadership on government projects.
BSRIA Living Laboratory Innovation Challenge
Final days for submission, closing March 29.
Windows, their frames, forms, factors and functions.
The hidden subtleties of U-Value calculations
Different contexts and what to include as variables.
A brief run down with related articles.
Electrical sector calls for safer public EV charge points
Serious concerns about electrical safety in the public domain.
Building Blocks manifesto presented to parliament
Architects Declare call in for support of five critical policies.
The four elements of project management with APM
Analysis, expectations, collaborative communication and partnerships.
City of London launches Heritage Building Retrofit Toolkit
Empowering owners to initiate necessary adaptations.
Guidance on RAAC in listed buildings
Published by Purcell, endorsed by IHBC, SPAB and C20.
Learning from the past.
Reluctance to hire people with criminal convictions revealed
Employing People with Criminal Convictions Report.
Tackling unconscious bias; Women's History Month
Personal reflections, as the last week of March approaches.