Rolling wave programming
Programmes describe the sequence in which tasks must be carried out so that a project (or part of a project) can be completed on time. They offer a view of how the project will be divided into activities, the duration of those activities, and logic links to preceding and succeeding activities.
Programmes may be depicted as Gantt charts, bar charts, line-of-balance diagrams, pure logic diagrams, time-scaled logic diagrams, time-chainage diagrams and so on.
For more information see: Programme for building design and construction.
Rolling wave programming (or rolling wave planning) is a method of programme development in which the details of the programme are progressively elaborated as the project proceeds. This is based on the assumption that it will be possible to develop the plan for specific activities in more detail closer to the time that they are actually executed.
Ref The Society of Construction Law Delay and Disruption Protocol, 2nd edition, published in February 2017 by the Society of Construction Law (UK).
NB Earned Value Management Handbook, Published by the Association for Project Management in March 2013 suggests that planning packages (PPs): ‘…represent work that cannot yet be planned as work packages because of a lack of detailed information. They must be converted into work packages before they can commence.’
It proposes that: ‘The requirement for a periodic conversion, from planning package to work package, is the result of setting up the project using rolling wave planning, whereby only the current phase of a project is planned in detail and future phases are planned in outline. The conversion process is a fundamental aspect of project control using EVM (earned value management) and results in a more controlled project baseline.’
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Mental Health Awareness Week with ABS
Architects Benevolent Society programme of activity.
CLC publishes domestic retrofit competency framework
Roadmap of Skills for net zero.
May 13-19: Moving more for our mental health.
Understanding is key to conservation.
Open industry engagement survey seeks responses
Institutions and the importance of engagement.
National Retrofit Hub unveils new guide
Digital Building Logbooks and Retrofit: An Introduction.
Top 50 firms awarded 52bn of projects in the last year
New engineering data shows.
Enhancing construction site reporting efficiency
Through digitisation and the digital revolution.
Noise in the built environment
BSRIA guide TG 20/2021.
17,000 people suffer conditions as a result of exposure to excessive noise at work.
Turning down the noise: Auditory health
A pervasive risk with far-reaching consequences.
Getting the most out of heat pumps and heating
How heat pumps work and how they work best.
Plumbing and heating for successful retrofit and renovation
Low temperature underfloor systems and heat pumps.
Cost-of-living crisis and home improvement plans
Starting on the right footing and top tips for projects.
Delays on construction projects
Types, mitigation and the acceleration of works.
From Chaucer to Fawlty Towers.
Electrotechnical excellence, now open for entries.
Net zero electricity grids BSRIA guide NZG 5/2024
Outlining the changes needed to transition to net zero.
CIOB Global Student Challenge 2024
Universitas Indonesia wins for second year running.