Advance payment bond for construction contracts
If the client agrees to make an advance payment (sometimes referred to as a down payment) to a supplier, a bond may be required to secure the payment against default by the contractor. This is referred to as an advance payment bond (APB), advance payment guarantee or advance stage payment.
For more information, see Advance payment.
Typically on a construction project an advanced payment bond will be required by the client if the contractor requests advance payment to help them meet significant start up or procurement costs that may have to be incurred before construction begins.
For example, where the contractor has had to purchase high-value plant, equipment or materials specifically for the project. The bond will protect the client in the event that the contractor fails to fulfil its contractual obligations, for example if the contractor becomes insolvent.
An advance payment bond will normally be an on-demand bond, meaning that the bondsman pays the amount of money set out in the bond immediately on demand, without any preconditions having to be met. This is as opposed to a a conditional bond (or default bond) where the bondsman is only liable if it has been established that there has been a breach of contract.
Advance payment bonds must be very carefully drafted to set out the circumstances for payment and to make clear that they are on-demand bonds.
A ‘vesting certificate’ or ‘certificate of vesting’ may be required from the contractor (or sub-contractors or suppliers), certifying that ownership of goods, plant or materials listed in a schedule will transfer from one party to the other upon payment and confirming that they will be properly identified, separately stored, insured and are free from encumbrances (such as retention of title).
For more information see: Vesting certificate.
[edit] Related articles on Designing Buildings
- Advance payment.
- Bid bond.
- Bonds in construction contracts
- Bonds and guarantees.
- Escrow.
- Materials on site.
- Off-site goods and materials.
- Off-site goods and materials - legal issues.
- On-demand bond.
- Parent company guarantee.
- Performance bond.
- Retention.
- Retention bond.
- Vesting certificate.
- Wuhan Guoyu Logistics Group Co Ltd & Anr v Emporiki Bank of Greece SA.
- Zero-coupon bond.
[edit] External references
- Rainy Sky S.A. v Kookmin Bank.
Featured articles and news
Grenfell Tower Inquiry announcement
Phase 2 hearings come to a close and the final report due in September.
Progress from Parts L, F and O: A whitepaper, one year on.
A replicated study to understand the opinion of practitioners.
A distinct type of countryside that should be celebrated.
Should Part O be extended to existing buildings?
EAC brands heatwave adaptation a missed opportunity.
Definition of Statutory in workplace and facilities management
Established by IWFM, BESA, CIBSE and BSRIA.
Tackling the transition from traditional heating systems
59% lack the necessary information and confidence to switch.
The general election and the construction industry
As PM, Rishi Sunak announces July 4 date for an election.
Home improvements swapped for green energy upgrades
As applications down since and desire to reduce bills up.
Eco apprenticeships continue help grow green workforce
A year after being recognised at the King's coronation.
The Use of Natural Insulation Materials in Retrofit
New paper from STBA with support from SDF.
National Retrofit Hub in partnership with InstallerSHOW.
Permitted development rights for agricultural buildings
The changes coming into effect as of May 21, 2024.
Biodiversity and the built environment digital series
The nature of building, with CIOB and CWP.
A call for prevention and sensitive re-use.
Risks to the long-term effectiveness of the BNG scheme
National Audit Office publish review of Biodiversity Net Gain.
The CIAT principal designer register
Providing assurance and verification of the capability and competence of registered ATs.
Scottish Government action to reach net-zero targets
Retrofit expert group highlight critical actions needed.
Comments