Project lifecycle for major road projects
Contents |
[edit] Introduction
The project control framework (PCF) is a joint Department for Transport and Highways Agency approach to managing major projects, which comprises:
- A standard project lifecycle.
- Standard project deliverables.
- Project control processes.
- Governance arrangements.
The project lifecycle for major road projects is set out in the project control framework Handbook v2 April 2013.
Once initiated a project enters the major projects lifecycle which breaks down the three phases of the project control framework into seven stages shown below:
[edit] Major projects lifecycle
[edit] Pre-project
0: Strategy, shaping and prioritisation
[edit] Options phase
1: Option identification
- Identify options to be taken to public consultation.
- Assess options in terms of environmental impact, traffic forecasts and economic benefits.
- Refine the cost estimate of options (including an allowance for risk).
2: Option selection
- Carry out public consultation including exhibitions.
- Analyse comments received and select a preferred option.
- Refine the cost estimate for preferred option (including allowance for risk).
- Refine the environmental impact assessment, traffic forecasts, and economic benefits following public consultation if required.
- Produce an outline business case.
- Announce the preferred route.
[edit] Development phase
- If early contractor involvement procurement method selected, appoint contractor.
- Carry out surveys (such as topographical, geotechnical, environmental).
- For Planning Act 2008 schemes hold community consultation including exhibitions, complete consultation report and resolve or rebut outstanding issues.
- Complete and freeze the preliminary design of the preferred route.
- Prepare draft Planning Act 2008 development consent order (or Highways Act 1980 orders if the scheme is below the threshold for a nationally significant infrastructure project (NSIP)), as appropriate.
- Complete the environmental assessment and prepare the environmental statement.
- Agree initial target cost with ECI contractor (if applicable).
4: Statutory procedures and powers
- Publish notice of acceptance of Planning Act 2008 draft development consent order and application (or notice of draft Highways Act 1980 orders if the scheme is below the threshold for a NSIP) and environmental statement as appropriate (exhibitions may be considered for Highways Act 1980 orders).
- Arrange public inquiry for Highways Act 1980 orders (if required).
- Under the Planning Act 2008 the Planning Inspectorate will decide on the preliminary meeting and examination of the application for development consent. We will need to register and comment as an interested party (the developer).
- Present evidence and rebuttals to objections for Highways Act 1980 orders at inquiry.
- The Planning Inspectorate panel or inspector will make recommendations to the Secretary of State.
- Issue secretary of state’s decision letter confirming whether orders/development consent are to be confirmed as published in draft, rejected or amended.
5: Construction preparation
- Confirm orders/development consent and respond to any high court challenges (if any).
- Obtain approval to any advance works or advance statutory undertakers diversions.
- Agree costs of construction with the contractor. If ECI is procurement method, agree final target cost.
- Produce the final business case.
- For Planning Act 2008 schemes place details of land to be acquired on deposit and publish a notice to say where these can be inspected.
- Obtain notice to proceed
[edit] Construction phase
6: Construction, commissioning and handover
- Issue notices to treat and enter take possession of land.
- Complete detailed design.
- Construct and commission scheme.
- Hand over asset for operation with as-built drawings and health and safety file.
- Open scheme to traffic.
7: Closeout
- Agree final account with contractor.
- Contractor completes outstanding works (or re-work).
- Complete a review of project.
[edit] Related articles on Designing Buildings Wiki
- Comparison of BIM work stages.
- Designing Buildings Wiki project plans.
- Gateway.
- Governance for Railway Investment Projects (GRIP).
- Great Musgrave: infilled bridge a sad reflection on state of the industry.
- OGC gateway review process.
- RIBA plan of work.
- RIBA plan of work v project plans v OGC gateways.
Featured articles and news
What it is and how to use it.
Investors in People: CIOB achieves gold
Reflecting a commitment to employees and members.
Scratching beneath the surface; a guide to selection.
ECA 2024 Apprentice of the Year Award
Entries open for submission until May 31.
UK gov apprenticeship funding from April 2024
Brief summary the policy paper updated in March.
For the World Autism Awareness Month of April.
70+ experts appointed to public sector fire safety framework
The Fire Safety (FS2) Framework from LHC Procurement.
Project and programme management codes of practice
CIOB publications for built environment professionals.
The ECA Industry Awards 2024 now open !
Recognising the best in the electrotechnical industry.
Sustainable development concepts decade by decade.
The regenerative structural engineer
A call for design that will repair the natural world.
Buildings that mimic the restorative aspects found in nature.
CIAT publishes Principal Designer Competency Framework
For those considering applying for registration as a PD.
BSRIA Building Reg's guidance: The second staircase
An overview focusing on aspects which most affect the building services industry.
Design codes and pattern books
Harmonious proportions and golden sections.
Introducing or next Guest Editor Arun Baybars
Practising architect and design panel review member.