Last edited 19 Oct 2016



[edit] Introduction

Prefabrication is a construction industry term used to describe assemblies that are manufactured under factory conditions and then transported to construction sites for incorporation into building and civil engineering works.

[edit] Post-war residential tower blocks and residential building.

The acute shortage of post war housing led to a boom in high-rise apartment blocks and contractors turned to prefabricated panelised wall and floor system building in an attempt to meet demand.

However, the jointing systems used and the failure to hide large joints produced monotonous, ugly housing stock, often with condensation problems.

[edit] Ronan point

A gas explosion in 1968 at Ronan Point resulted in the multiple collapse of an entire corner of a twenty six floor tower block killing four people and badly injuring seventeen residents. A pensioner striking a match to boil water for tea, lit the leaking gas from a joint in her newly installed cooker, the resulting explosion was small enough to blow her through the kitchen door and save her life. It lifted the ceiling/floor slab and pushed the wall out resulting in a house of cards type collapse (called progressive collapse). The building was only partly occupied at the time. The resulting lack in public confidence brought this type of construction in the UK to a rapid halt from which it has never completely recovered, despite the tightening of regulations. BBC Archive, ITN news and Wikipedia page have details.

[edit] Building Regulations

The collapse caused an amendment in the building regulations, which was subsequently included in the new versions - it was that important a collapse. This imposed on designers a robustness clause where if one element failed than the others would have to be strong enough to take the loads, and allow the occupants to escape. Load paths and transfer became vitally important to architects and structural engineers. It was progressive collapse that caused the World Trade Towers to fall in 9/11 attacks and a lack of robustness, especially considering a plane flew into the Empire state building causing little structural damage - note: slightly smaller plane and corresponding fuel tank, stone cladding and heaver steel framing and riveted connections. WTC did not have to comply with building regulations as it was built in government land (NY Port Authority) and the NY regulations did not have any clauses for robustness at the time either.

[edit] Others

However, there are a great many successful factory produced schemes of this nature in Europe and the Far East. Japan has been producing beautifully detailed houses for three decades providing many options to the customer, who approaches purchase in much the same way as ordering a new car from a production line. The Scandinavians export superbly insulated timber houses with triple glazing and Germany offers beautifully detailed unashamedly modern prefabricated translucent glass and steel houses particularly suited to sites with outstanding views.

[edit] Common use

[edit] Repetition

The handling, transportation, craneage and erection costs of prefabrication have to be weighed against in-situ alternatives. Economic justification is often dependent on high volume and repetition. This has led to use in applications such as residential blocks, hotels and houses. Architectural success in disguising panel joints has improved public opinion, helping to combat the perception that prefabrication is unsightly and cheap.

[edit] Time

Where there is a short programme for construction, and so time has a higher priority than cost, prefabrication can allow parallel working on different aspects of a project.

For example:

  • The Trustees of Ascot Racecourse were only prepared to lose one year of Royal Ascot racing during which the old grandstand had to be demolished and replaced with a new 50,000 sq m equivalent. As a result, the frame and steppings were manufactured while racing took place under the old facilities. The new structure, consisting of composite concrete and steel, was installed in record time.
  • Bridges over motorways are often prefabricated to avoid causing traffic congestion.
  • Avalanche shelters have a narrow timescale between seasons in which construction can take place so are mostly prefabricated structures.

[edit] Quality

The quality achievable with factory prefabrication is generally higher than can be achieved on site. This particularly applies to welding and hot trades such as pipe work and mechanical services. Back to back toilet and basin units mounted on steel framework are commonplace. Even mini plant rooms lend themselves to prefabrication. This can save a lot of complex site work in confined spaces.

[edit] Advantages

The advantages of prefabrication include:

  • Programme savings due to the ability to progress work as a parallel operation in a factory and on a construction site.
  • Factory tolerances and workmanship is of a higher quality and consistency to that achieved on site.
  • There tends to be less waste.
  • Independence from adverse weather and winter working.
  • An alternative means of production where there may be shortages of local skilled labour.
  • Access to cheaper labour markets. For instance two hundred prefabricated timber lodges for short holiday lets in Pembrokeshire were sourced from Eastern Europe.
  • Reduction in learning curves.
  • Greater programme certainty.
  • The factory environment can allow better safety than the construction site.

[edit] Disadvantages

The disadvantages of prefabrication include:

  • Road transport maximum widths.
  • The need for police escorts.
  • Height restrictions under bridges.
  • Daytime traffic restrictions in city centres.
  • Maximum load capacities of site craneage and temporary gantries.
  • Space and building elements held back for access/installation routes.
  • Additional cost of temporary bracing for transportation and/or lifting or permanent framing to support prefabricated assemblies.
  • Additional cost of pre-assembly in the factory prior to dismantling for transport and delivery.
  • The insitu work abutting prefabricated assemblies requires a higher degree of accuracy than is normally associated with on-site building work to avoid interface problems.
  • A mistake in the mass production of prefabricated elements ahead of the measurable site work is a serious risk. Reputedly there is a field in which sixty prefabricated concrete staircases are buried as they had been incorrectly manufactured for a tower block in the City of London.
  • Sustainability is an issue regarding the transportation of the materials to the construction site.

[edit] Find out more

[edit] Related articles on Designing Buildings Wiki

[edit] External references