Open tendering of construction works
A 'tender' is a submission made by a prospective supplier in response to an invitation to tender. It makes an offer for the supply of goods or services. In construction, the main tender process is generally the selection, by the client, of a contractor to construct the works. However, procurement routes have become more complex, so tenders may now be sought for a wide range of goods and services.
Irrespective of the goods or services that are being sought, securing tenders generally follows one of a number of basic procedures:
Open tendering allows anyone to submit a tender to supply the goods or services that are required. Generally, an advert will be placed giving notice that the contract is being tendered, offering an equal opportunity to any organisation to submit a tender.
On larger projects, there may then be a pre-qualification process that produces a short-list of suitable suppliers from the respondents expressing interest in the contract. This short list will then be invited to prepare tenders. The selection of a short list can include pre-qualification questionnaires and interviews. This sort of pre-qualification process is not the same as selective tendering. Selective tendering only allows suppliers invited from a pre-selected list to take part in the tender process.
Open tendering has been criticised for being a slow and costly process, attracting tenders or expressions of interest from large numbers of suppliers, some of whom may be entirely unsuitable for the contract and as a result it can waste a great deal of time, effort and money. However, open tendering offers the greatest competition and has the advantage of allowing new or emerging suppliers to try to secure work and so can facilitate greater innovation. The number of firms tendering can be reduced (ideally to a maximum of 6) by a pre-qualification process, and if this uses a standard pre-qualification questionnaire, then the time wasted by unsuitable applicants can be minimised.
Whilst often seen to be more efficient, selective tendering can exclude potential suppliers, it can be seen to introduce bias into the process, and it can result in prospective suppliers continually contacting clients and consultants to check that they are on the appropriate lists.
On public projects, or projects that include an element of public funding, it may be necessary to advertise contracts as a requirement of the Public Contracts Regulations. This is intended to open up public procurement within the European Union and to ensure the free movement of supplies, services and works (see OJEU for more information).
Open tendering can be either single stage or two stage. Two-stage tendering is used to allow early appointment of a supplier, prior to the completion of all the information required to enable them to offer a fixed price. In the first stage, a limited appointment is agreed, allowing them to begin work and ine a fixed price is negotiated for the contract.
For a more detailed description of the procedures for open tendering, see Tender.
[edit] Related articles on Designing Buildings
- Appointing consultants.
- Call-off contract.
- Due diligence when selecting contractors or subcontractors.
- E-tendering.
- Invitation to tender.
- Mid-tender Interviews.
- OJEU procurement rules.
- Pre-qualification questionnaire.
- Pre-tender Interviews.
- Procurement routes.
- Reverse auction.
- Selective tender.
- Tender documentation.
- Tender evaluation.
- Tender processes for construction contracts
- Tender.
- Two stage tender.
Featured articles and news
Open industry engagement survey seeks responses
Institutions and the importance of engagement.
National Retrofit Hub unveils new guide
Digital Building Logbooks and Retrofit: An Introduction.
Top 50 firms awarded 52bn of projects in the last year
New engineering data shows.
Enhancing construction site reporting efficiency
Through digitisation and the digital revolution.
Noise in the built environment
BSRIA guide TG 20/2021.
17,000 people suffer conditions as a result of exposure to excessive noise at work.
Turning down the noise: Auditory health
A pervasive risk with far-reaching consequences.
Getting the most out of heat pumps and heating
How heat pumps work and how they work best.
Plumbing and heating for successful retrofit and renovation
Low temperature underfloor systems and heat pumps.
Cost-of-living crisis and home improvement plans
Starting on the right footing and top tips for projects.
Delays on construction projects
Types, mitigation and the acceleration of works.
From Chaucer to Fawlty Towers.
Electrotechnical excellence, now open for entries.
Net zero electricity grids BSRIA guide NZG 5/2024
Outlining the changes needed to transition to net zero.
CIOB Global Student Challenge 2024
Universitas Indonesia wins for second year running.
ECA 2024 Apprentice of the Year Award
Entries open for submission until May 31.