Frustration in construction contracts
Frustration occurs when circumstances that are not the fault of either party to a contract mean it is impossible to continue with the contract. As a result, the contract comes to an end without either party being considered to be in breach. However, the parties must be certain that a frustration event has occurred so as not to be in breach of contract.
Frustration is a common legal principle, but it is applied as narrowly as possible by the courts - it does not cover contracts that were always going to be impossible to perform. For example, it would not apply in the case of a contract to construct a tall building that could not be fulfilled because the ground conditions were completely unsuitable.
Identifying the contractual obligations of the parties at the date of the contract is key to being able to establish the conditions for frustration.
Some events that may lead to a frustrated contract include:
- The government imposing unforeseen restrictions on building.
- Laws being passed that make it illegal to undertake what was promised under the contract
- The building where works were to be carried out being destroyed.
- An event that was crucial for the contractual obligations being cancelled.
Sometimes a party may try to claim a contract is frustrated when they are obligated to make payments in a different currencies which then fluctuates. However, this does not necessarily amount to frustration.
Events that do not alter the obligations but instead delay performance, such as a workforce strike, don’t necessarily amount to frustration. However, it might do should the events have a particularly serious effect on the obligations or if the delay is particularly long.
Force majeure provisions might provide for circumstances that could otherwise be considered frustration events, and so result in termination of the contract. However, generally, force majeure (for example, exceptionally adverse weather conditions) is considered a relevant event which construction contracts allow for by an extension of time rather than termination.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Top 50 firms awarded 52bn of projects in the last year
New engineering data shows.
Enhancing construction site reporting efficiency
Through digitisation and the digital revolution.
Noise in the built environment
BSRIA guide TG 20/2021.
17,000 people suffer conditions as a result of exposure to excessive noise at work.
Turning down the noise: Auditory health
A pervasive risk with far-reaching consequences.
UK Construction Week, London is here !
Debuting major international pavilions and much more.
Getting the most out of heat pumps and heating
How heat pumps work and how they work best.
Plumbing and heating for successful retrofit and renovation
Low temperature underfloor systems and heat pumps.
Cost-of-living crisis and home improvement plans
Starting on the right footing and top tips for projects.
Delays on construction projects
Types, mitigation and the acceleration of works.
From Chaucer to Fawlty Towers.
Electrotechnical excellence, now open for entries.
Net zero electricity grids BSRIA guide NZG 5/2024
Outlining the changes needed to transition to net zero.
CIOB Global Student Challenge 2024
Universitas Indonesia wins for second year running.
ECA 2024 Apprentice of the Year Award
Entries open for submission until May 31.