Approved Document B Fire Safety, Volume 2, Buildings other than dwellinghouses (2019 edition), defines fire resistance as:
'The ability of a component or a building to satisfy, for a stated period of time, some or all of the appropriate criteria given in the relevant standard.'
Fire resistance is a measure of one or more of the following:
- Resistance to collapse (loadbearing capacity), which applies to loadbearing elements only, denoted R in the European classification of the resistance to fire performance.
- Resistance to fire penetration (integrity), denoted E in the European classification of the resistance to fire performance.
- Resistance to the transfer of excessive heat (insulation), denoted I in the European classification of the resistance to fire performance.
Fire resistance is measured in minutes. This relates to time elapsed in a standard test and should not be confused with real time.
Performance in terms of the fire resistance to be achieved by elements of structure, doors and other forms of construction is classified in accordance with BS EN 13501.
Other information about fire resistance in the approved document includes:
- Table B3 gives the specific requirements for each element of structure.
- Table B4 sets out the minimum periods of fire resistance for elements of structure.
- Table B5 sets out limitations on the use of uninsulated fire resisting glazed elements.
NB PAS 9980:2022, Fire risk appraisal of external wall construction and cladding of existing blocks of flats – Code of practice, published by BSI Standards Limited in 2022, defines fire resistance as the: ‘…ability of an item to fulfil for a stated period of time the required loadbearing capacity and/or integrity and/or thermal insulation, and/or other expected duty specified in a standard fire resistance test. NOTE This is not the time that the item can withstand exposure to any specific real fire without loss of its required performance.’
[edit] Related articles on Designing Buildings
- Adhesives.
- BS 476.
- BS EN 13501-1.
- Cavity barrier.
- Compartment floor.
- Dry riser.
- Escape route.
- Fire.
- Fire and rescue service.
- Fire blanket.
- Fire collar.
- Fire compartment.
- Fire damper.
- Fire detection and alarm systems.
- Fire door.
- Fire safety design.
- Fire-separating element.
- Fire separation.
- Fire-stopping.
- Firefighting route.
- Intumescent coatings.
- Intumescent strip.
- Joint fire code.
- Mastic asphalt flooring.
- Means of escape.
- Passive fire protection is a vital tool in any fire strategy.
- Place of special fire hazard.
- Protected escape route.
- Protected stairway.
- Sacrificial timber.
- Supporting construction.
- Thermoplastic material.
- Unprotected escape route.
- Wet riser.
Featured articles and news
Top 50 firms awarded 52bn of projects in the last year
New engineering data shows.
Enhancing construction site reporting efficiency
Through digitisation and the digital revolution.
Noise in the built environment
BSRIA guide TG 20/2021.
17,000 people suffer conditions as a result of exposure to excessive noise at work.
Turning down the noise: Auditory health
A pervasive risk with far-reaching consequences.
UK Construction Week, London is here !
Debuting major international pavilions and much more.
Getting the most out of heat pumps and heating
How heat pumps work and how they work best.
Plumbing and heating for successful retrofit and renovation
Low temperature underfloor systems and heat pumps.
Cost-of-living crisis and home improvement plans
Starting on the right footing and top tips for projects.
Delays on construction projects
Types, mitigation and the acceleration of works.
From Chaucer to Fawlty Towers.
Electrotechnical excellence, now open for entries.
Net zero electricity grids BSRIA guide NZG 5/2024
Outlining the changes needed to transition to net zero.
CIOB Global Student Challenge 2024
Universitas Indonesia wins for second year running.
ECA 2024 Apprentice of the Year Award
Entries open for submission until May 31.
Comments