Highway drainage
Contents |
[edit] Introduction
The construction of roads affects the natural surface and subsurface drainage pattern of watersheds or hill-slopes. The provision of adequate drainage is important to prevent the accumulation of excess water or moisture on or within road constructions that can adversely affect their material properties, compromise overall stability and affect driver safety. Drainage must cope with water from the carriageways, hard shoulders, foot/cycle paths, verges, and adjacent catchment areas.
The design of highway drainage will depend on several factors, including:
- The intensity of rainfall expected.
- The size of catchment area.
- The permeability of the surfaces.
The road camber or cross-fall should be designed to cope with heavy water run-off. Insufficient cross-fall can increase the risk of vehicles skidding or aquaplaning on the surface water. The standard cross-fall for roads is usually taken as 1:40, although the camber will vary depending on the individual requirements of the road.
[edit] Urban roads
Surface water is generally collected in channels at the road-side and discharged through gullies (drainage gratings at the edges of the road) into storm water sewers. Gullies are typically positioned at intervals of 25-30 m, depending on the road width and nature of the cross-fall. Gully covers can be either top opening or side opening.
To reduce the number of required drainage points, pavings and verges should be graded towards the channel.
Culverts may also be used. A culvert is a closed conduit or tunnel used to convey water from one area to another, normally from one side of a road to the other side.
For more information, see Culvert.
[edit] Rural roads
Minor roads usually use simple openings or channels which feed into roadside ditches.
Most main roads use a system of gullies and piped sewers. However, soakaways may also be used to discharge water, these are large underground chambers into which water flows from a gully. Water collects and gradually soaks through holes into the surrounding ground or to streams and roadside ditches.
For more information, see Soakaway.
For roads with hard shoulders, it is usual for the kerb to be kept flush with the road surface, with a precast concrete channel placed at the outside edge to drain water. This channel discharges water into gullies.
[edit] Related articles on Designing Buildings Wiki:
- Bituminous mixing and laying plant.
- Catchment flood management plans.
- Code of Practice for Ironwork Systems Installation and Refurbishment.
- Drainage.
- Gulley.
- Highway engineers and drainage.
- Infrastructure.
- Kerbs.
- Manhole.
- Manhole cover.
- Overview of the road development process.
- Pavement.
- Planning for floods.
- Pumps and dewatering equipment.
- Road construction.
- Road improvement scheme consultation.
- Road joints.
- Runway construction.
- Section 50 agreement.
- Sewer construction.
- Soakaway.
- Successful road kerb trial.
- Sustainable urban drainage systems SUDS.
- Types of road and street.
- Water engineering.
[edit] External references
- ‘Introduction to civil engineering construction’ (3rd ed.), HOLMES, R., The College of Estate Management (1995)
- ‘Building Construction Handbook’ (6th ed.), CHUDLEY, R., GREENO, R., Butterworth-Heinemann (2007)
Featured articles and news
National Retrofit Hub unveils new guide
Digital Building Logbooks and Retrofit: An Introduction.
Top 50 firms awarded 52bn of projects in the last year
New engineering data shows.
Enhancing construction site reporting efficiency
Through digitisation and the digital revolution.
Noise in the built environment
BSRIA guide TG 20/2021.
17,000 people suffer conditions as a result of exposure to excessive noise at work.
Turning down the noise: Auditory health
A pervasive risk with far-reaching consequences.
UK Construction Week, London is here !
Debuting major international pavilions and much more.
Getting the most out of heat pumps and heating
How heat pumps work and how they work best.
Plumbing and heating for successful retrofit and renovation
Low temperature underfloor systems and heat pumps.
Cost-of-living crisis and home improvement plans
Starting on the right footing and top tips for projects.
Delays on construction projects
Types, mitigation and the acceleration of works.
From Chaucer to Fawlty Towers.
Electrotechnical excellence, now open for entries.
Net zero electricity grids BSRIA guide NZG 5/2024
Outlining the changes needed to transition to net zero.
CIOB Global Student Challenge 2024
Universitas Indonesia wins for second year running.
ECA 2024 Apprentice of the Year Award
Entries open for submission until May 31.