Level of effort
An activity is an operation or process consuming time and possibly other resources. An individual or work team can manage an activity. It is a measurable element of the total project programme.
The term ‘level of effort’ can be used in relation to:
‘…a special activity type in programming software with unique qualities for duration. The software calculates the duration of a level of effort activity based on dates from its predecessor(s) and successor(s) rather than having a duration assigned to the particular activity. They are supposed to be used for support work, such as meetings, which occur during the timeframe of the predecessors and successors. In practice, they are sometimes also used in the older context of ‘hammocks’ but are not in fact a hammock.'
A hammock can be used to refer to an activity representing the period from the start of an activity to the completion of another. It is sometimes used as a way of summarising the duration of a number of activities in a programme as one single duration.
Ref Society of Construction Law Delay and Disruption Protocol, 2nd edition, February 2017, published by the Society of Construction Law (UK). https://www.scl.org.uk/resources/delay-disruption-protocol
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Top 50 firms awarded 52bn of projects in the last year
New engineering data shows.
Enhancing construction site reporting efficiency
Through digitisation and the digital revolution.
Noise in the built environment
BSRIA guide TG 20/2021.
17,000 people suffer conditions as a result of exposure to excessive noise at work.
Turning down the noise: Auditory health
A pervasive risk with far-reaching consequences.
UK Construction Week, London is here !
Debuting major international pavilions and much more.
Getting the most out of heat pumps and heating
How heat pumps work and how they work best.
Plumbing and heating for successful retrofit and renovation
Low temperature underfloor systems and heat pumps.
Cost-of-living crisis and home improvement plans
Starting on the right footing and top tips for projects.
Delays on construction projects
Types, mitigation and the acceleration of works.
From Chaucer to Fawlty Towers.
Electrotechnical excellence, now open for entries.
Net zero electricity grids BSRIA guide NZG 5/2024
Outlining the changes needed to transition to net zero.
CIOB Global Student Challenge 2024
Universitas Indonesia wins for second year running.
ECA 2024 Apprentice of the Year Award
Entries open for submission until May 31.