Interim certificates in construction contracts
Contents |
[edit] What are interim certificates?
Interim certificates provide a mechanism for the client to make payments to the contractor during the construction process, before the works are complete. The Housing Grants, Construction and Regeneration Act, states that a party to a construction contract in excess of 45 days is entitled to interim or stage payments.
[edit] How are interim payments made?
Interim payments can be agreed in advance and paid at particular milestones, but they are more commonly, regular payments, the value of which is based on the value of work that has been completed (this is the actual value of the work completed, taking into account variations, etc.).
The amount of these payments is entered onto an interim certificate (generally valued by the cost consultant, perhaps having taken advice from the lead designer) and the client must honour the certificate within the period stipulated by the contract.
If the client intends to pay a different amount from that shown on the interim certificate, then they must give notice to the contractor of the amount they intend to pay and the basis for its calculation (pay less notice)
For more information see: Housing Grants, Construction and Regeneration Act.
[edit] How are interim payments valued?
The value of interim certificates is the value of the work completed, less any amounts already paid, less retention. Half of this retention will be released on certification of practical completion and the other half upon issue of the certificate of making good defects.
Interim certificates should make clear the amount of retention and a statement should also be prepared showing retention for nominated sub-contractors if there are any. The contract may require that retention is kept in a separate bank account and that this is certified. In this case, the client will generally keep any interest paid on the account.
For more information see: Retention.
There may be provision to include the value of particularly costly materials that the contractor has not yet delivered to site. This allows the contractor to order items in good time, without incurring unnecessary long-term expense, but does put the client at some risk if the contractor becomes insolvent.
For more information see: Off-site goods and materials.
On design and build projects, the amounts certified as payable may be based on the contract sum analysis.
The contract conditions provide that the contract administrator must issue an interim certificate within five calendar days of the due date whether or not the contractor has issued an interim payment application. This five calendar day period is set by statute in the Housing Grants, Construction Regeneration Act 1996 as amended by the Local Democracy, Economic Development and Construction Act 2009.
For more information see: Payment notice.
[edit] Related articles on Designing Buildings
- Activity schedule.
- Certificate of making good defects.
- Certificates in the construction industry.
- Contract sum analysis.
- Cost value reconciliation.
- Drawdown.
- Due date.
- Final certificate.
- Housing Grants, Construction and Regeneration Act.
- Interim valuation.
- Off site materials.
- Milestone payment.
- Payment notice.
- Payments to nominated sub-contractors.
- Practical completion.
- Retention.
[edit] External references
- RICS Valuations for interim certificates.
- Allan K Construction contracts 2017 @qs 2 kings entertainment
Featured articles and news
How to revolutionise UK housing with MMC
CIC and Supply Chain Sustainability School unveil a plan.
From the UKs largest manufacturer and supplier of lime.
From mud bricks to smart concrete
A brief history from 7000BC to a future on the moon.
Regulator of Social Housing publishes latest fire safety report
Covering remediation of 11 metre plus social housing sector buildings.
Apartment and Duplex Defects Remediation Bill 2024
Approved for priority drafting by Government of Ireland.
The long list with in the frame of key historical events.
Competence frameworks for sustainability in the built environment
Code of practice, core criteria consultation draft for comment.
UK Net Zero Carbon Buildings Standard Sept update
Pilot version for testing and feedback on its adoption due.
New Floods Resilience Taskforce
With a wet met office autumn prediction.
National Retrofit Hub takeover of Net Zero stage
At Birmingham UK Construction Week in October.
AT Awards 2024 finalists announced
With more to come, prior to the Awards ceremony in October.
London construction cools as hotspots appear nationally
Increases in the East of England, Yorkshire and Scotland.
ARB proposals for a new Architects Code
Announced in the shadow of the final Grenfell Inquiry report.
Combining human creativity and tech innovation now and in the future
Building automation and control systems market study
BSRIA 2024 North America BACS software & services.
Impact of digital technology on productivity in construction
New CIOB academy guidance for companies of all sizes.
Comments
[edit] To make a comment about this article, or to suggest changes, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.
Interim Payment Certificate is prepared by Consultant's Team Leader or Contractor's Project Manager's which reports Monthly progress schedule and progress cash-flow.