Sectional completion in construction contracts
Sectional completion refers to a provision within construction contracts allowing different completion dates for different sections of the works. This is common on large projects that are completed in sections, allowing the client to take possession of the completed parts whilst construction continues on others.
Sectional completion differs from partial possession in that it is pre-planned and defined in the contract documents.
If sectional completion is required, it must be an express term of the contract, and reflected by the fact that there are multiple completion dates rather than just one. The extent of each section must be clearly defined and liquidated damages, and the amount of retention that will be released must be specified for each section. There may also need to be clarification of how extension of time provisions will be applied if, for example, delays to one section of the works have a knock-on effect on other sections (the cascade effect).
In procedural terms, sectional completion is similar to normal completion and follows the usual handover procedures (see handover to client). However, some work within the section may remain outstanding, such as the completion of commissioning, operation and maintenance manuals and as built drawings, which will cross all sections.
It may exclude mechanical and electrical service systems which are reliant on total completion before they can be properly tested and commissioned. This means that their needs to be an agreed protocol for re-entry into completed sections for the contractors to complete outstanding work.
Sectional completion requires particular care to be taken regarding:
- Difficulties with logistics on site when different sections are in the possession of different parties.
- The protection of completed sections from ongoing work.
- The provision of appropriate insurance at all times for all sections.
- The adoption of appropriate health and safety measures to deal with risks resulting from occupation of areas adjacent to, or only accessible through ongoing construction works.
- The provision of appropriate security measures.
The consequences of sectional completion are that
- Half of the retention is released for that section.
- The Rectification Period begins for that section,
- The contractor’s responsibility for insuring the works (if applicable) ends for that section.
- The contractor’s liability for liquidated damages ends for that section.
- The employer is now responsible for any damages to the works for that section.
[edit] Related articles on Designing Buildings Wiki
- Building completion.
- Completion.
- Defects liability period.
- Defects.
- Difference between practical completion and partial possession.
- Early use.
- Extension of time.
- Handover to client.
- Liquidated damages.
- Loss and expense.
- Migration strategy.
- Occupation.
- Partial possession.
- Performance in use.
- Phased construction works.
- Possession.
- Post occupancy evaluation.
- Practical completion.
- Retention.
- Soft landings.
- Topping out.
- Work-to-complete list.
Featured articles and news
IHBC’s response to Parliamentary Committee
On Levelling-Up and Regeneration Bill.
Finalists for 2022 CIOB Awards revealed
Over 70 managers and organisations shortlisted for the 14 awards.
Types of building sensors on BD
From biometric to electrical current, chemical and more.
Government mandates detectors in rented homes
Changes are due to come into force on 1st October 2022.
80% of major government projects are rated red or amber
Heed advice and insight of this report IPA tells the government.
The end of the games but continued calls for action
From the Commonwealth Association of Architects.
CIOB respond to the government call for evidence
For the Levelling Up, Housing & Communities Committee.
How are buildings and their occupants responding to extreme heat?
BSRIA's Technical Director reflects on recent weather patterns.
Landownership in England in 1909
A national valuation to fund old-age pensions.
The world’s largest Commonwealth memorial to the missing.
Long after the end of the defects liability period.
BSRIA Occupant Wellbeing survey BOW
Occupant satisfaction and wellbeing in buildings.
Geometric form and buildings in brief
From the simple to the complex.
Understanding the changing nature of insulation
And the UK Government guidelines.
Three year action plan to improve equity, diversity and inclusion
Commitment agreed to by major built environment bodies.
The Construction Route – what needs to change?
Electrical skills, low carbon, high-tech and the building services revolution.
Deep geothermal power possibilities
Ultra-deep drilling with millimeter-wave beam technology.
BSRIA Briefing 2022- From the outside looking in
Looking at the built environment from space.
Competence requirements for principal contractors and designers
BSI standards 8671, 8672 and 8673.
Bringing life to burial grounds.
From failed modernism to twenty-minute neighbourhoods.
Design chill and design freeze
The gates process and change control.
Comments
Hi
I note sectional completion may not include the completed M&E or other element etc depending on how it is detailed in the contract docs.
What about partial possession (which I know is not preplanned) . Can partial possession cert be issued of there are still outstanding issues such as M&E, fire alarm etc.
Presumably not because it has to be complete ?
Niall
Question
what are the item we need to compile in sectional completion?
how was the
format of sectional completion?
how to describe it is sectional completion
when we want to give them it is sectional completion? or how to make sectional
completion certificate? is it like handover? do we need to produce as built
drawing as per hand over?
Answer --designing buildings 08:19, 30 June 2013 (BST)
This project is under construction. Certain section is completed. Can we make sectional completion even there is not stated sectional completion in the document contract. Does it wrong contractually?
Sectional completion is agreed before the contract is entered into. Partial possession or early use can be agreed whilst the contract is running.