Sectional completion in construction contracts
Sectional completion refers to a provision within construction contracts allowing different completion dates for different sections of the works. This is common on large projects that are completed in sections, allowing the client to take possession of the completed parts whilst construction continues on others.
Sectional completion differs from partial possession in that it is pre-planned and defined in the contract documents.
If sectional completion is required, it must be an express term of the contract, and reflected by the fact that there are multiple completion dates rather than just one. The extent of each section must be clearly defined and liquidated damages, and the amount of retention that will be released must be specified for each section. There may also need to be clarification of how extension of time provisions will be applied if, for example, delays to one section of the works have a knock-on effect on other sections (the cascade effect).
In procedural terms, sectional completion is similar to normal completion and follows the usual handover procedures (see handover to client). However, some work within the section may remain outstanding, such as the completion of commissioning, operation and maintenance manuals and as built drawings, which will cross all sections.
It may exclude mechanical and electrical service systems which are reliant on total completion before they can be properly tested and commissioned. This means that their needs to be an agreed protocol for re-entry into completed sections for the contractors to complete outstanding work.
Sectional completion requires particular care to be taken regarding:
- Difficulties with logistics on site when different sections are in the possession of different parties.
- The protection of completed sections from ongoing work.
- The provision of appropriate insurance at all times for all sections.
- The adoption of appropriate health and safety measures to deal with risks resulting from occupation of areas adjacent to, or only accessible through ongoing construction works.
- The provision of appropriate security measures.
The consequences of sectional completion are that
- Half of the retention is released for that section.
- The Rectification Period begins for that section,
- The contractor’s responsibility for insuring the works (if applicable) ends for that section.
- The contractor’s liability for liquidated damages ends for that section.
- The employer is now responsible for any damages to the works for that section.
[edit] Related articles on Designing Buildings Wiki
- Building completion.
- Completion.
- Defects liability period.
- Defects.
- Difference between practical completion and partial possession.
- Early use.
- Extension of time.
- Handover to client.
- Liquidated damages.
- Loss and expense.
- Migration strategy.
- Occupation.
- Partial possession.
- Performance in use.
- Phased construction works.
- Possession.
- Post occupancy evaluation.
- Practical completion.
- Retention.
- Soft landings.
- Topping out.
- Work-to-complete list.
Featured articles and news
Classroom electrician courses a 'waste of money'
Say experts from the Electrical Contractors’ Association.
Wellbeing in Buildings TG 10/2025
BSRIA topic guide updates.
With brief background and WELL v2™.
From studies, to books to a new project, with founder Emma Walshaw.
Types of drawings for building design
Still one of the most popular articles the A-Z of drawings.
Who, or What Does the Building Safety Act Apply To?
From compliance to competence in brief.
The remarkable story of a Highland architect.
Commissioning Responsibilities Framework BG 88/2025
BSRIA guidance on establishing clear roles and responsibilities for commissioning tasks.
An architectural movement to love or hate.
Don’t take British stone for granted
It won’t survive on supplying the heritage sector alone.
The Constructing Excellence Value Toolkit
Driving value-based decision making in construction.
Meet CIOB event in Northern Ireland
Inspiring the next generation of construction talent.
Reasons for using MVHR systems
6 reasons for a whole-house approach to ventilation.
Supplementary Planning Documents, a reminder
As used by the City of London to introduce a Retrofit first policy.
The what, how, why and when of deposit return schemes
Circular economy steps for plastic bottles and cans in England and Northern Ireland draws.
Reporting on Payment Practices and Performance Regs
Approved amendment coming into effect 1 March 2025.
Comments
Hi
I note sectional completion may not include the completed M&E or other element etc depending on how it is detailed in the contract docs.
What about partial possession (which I know is not preplanned) . Can partial possession cert be issued of there are still outstanding issues such as M&E, fire alarm etc.
Presumably not because it has to be complete ?
Niall
Question
what are the item we need to compile in sectional completion?
how was the
format of sectional completion?
how to describe it is sectional completion
when we want to give them it is sectional completion? or how to make sectional
completion certificate? is it like handover? do we need to produce as built
drawing as per hand over?
Answer --designing buildings 08:19, 30 June 2013 (BST)
This project is under construction. Certain section is completed. Can we make sectional completion even there is not stated sectional completion in the document contract. Does it wrong contractually?
Sectional completion is agreed before the contract is entered into. Partial possession or early use can be agreed whilst the contract is running.