Interim valuations and payments
Contents |
[edit] Introduction
Whether you are involved in administering hundreds of payments each month or just a few, these simple tips and guidance should help or provide a simple refresher.
Payments are simple once you get your head around the time-frames and the contractual process. Issuing applications in line with the contract terms in addition to being proactive with information is a big step of the way to ensuring payments are made on time.
This guidance is based on an unamended JCT D&B 2016. In most cases, the contract will be amended and worth reviewing to check for slight tweaks to the below.
[edit] Payment Application
The Payment Application under JCT D&B 2016 will be required to be issued no later than 4* days before the valuation date which may require a forecast up to the valuation date. Setting out the format of the application, in particular the detailed breakdown should reflect the Contract Sum, giving the same level of breakdown within the Contract.
Agreed variations are to be included and valued up to the valuation date. Where variations are unagreed or perhaps on a fast-moving project where changes have yet to be agreed, we recommend providing a detailed breakdown to the variation (including invoices, measures and photos) as well as a detailed justification for the variation including any reference to the contract.
We should add, that providing detailed breakdowns and justification for entitlement within a valuation does not relieve you of any contractual requirements for notification of changes – i.e. if the contract stipulates a specific change control process, this should still be adhered to. (We will detail this in a future article).
[edit] Payment Notice
Following a Payment Application, an assessment will take place to value the measured contract works and variations applied for. On reviewing the application there may be a disagreement with the works completed to date, the PQS should detail their assessment with the reason for any differences (including any photos or marked-up drawings to support the justification) in the assessment. This will then form your Payment Notice and under JCT D&B 2016, must be issued before 12 days* following the Valuation date. (The payment notice may also be referred to as the payment certificate).
[edit] Pay Less Notice
If after the Payment Notice is issued and something comes to light (for example incomplete works) which the PQS deems a deduction is to be made against the Payment Notice, a Pay Less Notice can be issued. This is required to be issued no later than 5 days before the final date for payment. The deduction should be broken down with justification for rates applied and clear reasoning for the deduction.
[edit] A few things to remember:
- The days stated above are calendar days not business days so, don’t get caught out.
- Where payments are scheduled out to a defined date, any application/valuations past this will not be due until the Final Account Payment.
- 7-day notice can be issued if payment is not made in line with the payment terms to suspend works until full payment is paid in line with the Payment Notice or Pay Less Notice.
- Where a Contract does not state payment terms, the Housing Grants Construction and Regeneration Act 1998 applies.
- These timeframes are based on the standard unamended JCT D&B 2016 – please check your contract for any amendments.
If you are unsure with any of the above or would like some assistance with interpretation of your contract and/or its amendments, contact your trusted quantity surveyor for help.
[edit] Related articles on Designing Buildings
- Construction invoice fraud.
- Construction supply chain payment charter.
- Construction contract certificates, notices and instructions.
- Contingent valuation.
- Due date.
- Fair payment practices.
- Interim certificate.
- Payment for construction.
- Payment notice.
- Pay less notice.
- Payment holiday.
- Payment schedule.
- Property valuation.
- Rating valuation.
- Relevant event.
- Residual valuation.
- Set off.
- The causes of late payment in construction.
- The Late Payment of Commercial Debts Regulations 2013.
- Valuation of interim payments.
Featured articles and news
Classroom electrician courses a 'waste of money'
Say experts from the Electrical Contractors’ Association.
Wellbeing in Buildings TG 10/2025
BSRIA topic guide updates.
With brief background and WELL v2™.
From studies, to books to a new project, with founder Emma Walshaw.
Types of drawings for building design
Still one of the most popular articles the A-Z of drawings.
Who, or What Does the Building Safety Act Apply To?
From compliance to competence in brief.
The remarkable story of a Highland architect.
Commissioning Responsibilities Framework BG 88/2025
BSRIA guidance on establishing clear roles and responsibilities for commissioning tasks.
An architectural movement to love or hate.
Don’t take British stone for granted
It won’t survive on supplying the heritage sector alone.
The Constructing Excellence Value Toolkit
Driving value-based decision making in construction.
Meet CIOB event in Northern Ireland
Inspiring the next generation of construction talent.
Reasons for using MVHR systems
6 reasons for a whole-house approach to ventilation.
Supplementary Planning Documents, a reminder
As used by the City of London to introduce a Retrofit first policy.
The what, how, why and when of deposit return schemes
Circular economy steps for plastic bottles and cans in England and Northern Ireland draws.
Reporting on Payment Practices and Performance Regs
Approved amendment coming into effect 1 March 2025.
Comments
[edit] To make a comment about this article, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.