Design management plan
A design management plan can be used to co-ordinate design activities. It should at least cover:
- Design responsibility matrix.
- Schedules of drawings to be produced by each discipline/specialist.
- Design programme, including key dates for reviews and information exchanges.
- Schedules of information required/release dates.
- The size and format of drawing types.
- Procedures for CAD / BIM (see BIM execution plan).
- Estimates of staff hours to be spent by designers on each element or drawing.
- Monitoring of design resources expended compared to planned estimates.
- Initiating procedures for design changes.
- Requirements for collateral warranties.
- Incorporation within the design schedule of key dates for review of design performance to check:
- Compliance with brief.
- Cost acceptance.
- Value engineering analysis.
- Health and safety issues.
- Completeness for tender.
The project manager, may use the agreed design management plan as a basis for monitoring and controlling the design process. However, integration of the work of consultant and specialists lies with the lead designer. For certain elements of the project, different leads may be nominated, however, these roles will always come under the direction of the lead designer for co-ordination.
The text in this article is based on an extract from PROJECT MANAGEMENT, by Eric Stokes and Saleem Akram. The original manual was published in 2008. It was developed within the scope of the LdV program, project number: 2009-1-PL1-LEO05-05016 entitled “Common Learning Outcomes for European Managers in Construction”. It is reproduced here in a slightly modified form with the kind permission of the Chartered Institute of Building.
--CIOB
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
IHBC’s response to Parliamentary Committee
On Levelling-Up and Regeneration Bill.
Finalists for 2022 CIOB Awards revealed
Over 70 managers and organisations shortlisted for the 14 awards.
Types of building sensors on BD
From biometric to electrical current, chemical and more.
Government mandates detectors in rented homes
Changes are due to come into force on 1st October 2022.
80% of major government projects are rated red or amber
Heed advice and insight of this report IPA tells the government.
The end of the games but continued calls for action
From the Commonwealth Association of Architects.
CIOB respond to the government call for evidence
For the Levelling Up, Housing & Communities Committee.
How are buildings and their occupants responding to extreme heat?
BSRIA's Technical Director reflects on recent weather patterns.
Landownership in England in 1909
A national valuation to fund old-age pensions.
The world’s largest Commonwealth memorial to the missing.
Long after the end of the defects liability period.
BSRIA Occupant Wellbeing survey BOW
Occupant satisfaction and wellbeing in buildings.
Geometric form and buildings in brief
From the simple to the complex.
Understanding the changing nature of insulation
And the UK Government guidelines.
Three year action plan to improve equity, diversity and inclusion
Commitment agreed to by major built environment bodies.
The Construction Route – what needs to change?
Electrical skills, low carbon, high-tech and the building services revolution.
Deep geothermal power possibilities
Ultra-deep drilling with millimeter-wave beam technology.
BSRIA Briefing 2022- From the outside looking in
Looking at the built environment from space.
Competence requirements for principal contractors and designers
BSI standards 8671, 8672 and 8673.
Bringing life to burial grounds.
From failed modernism to twenty-minute neighbourhoods.
Design chill and design freeze
The gates process and change control.
Comments
This is a really useful resource for teaching how to discharge the duties of the Principal Designer under CDM 2015.
Like the Principal Contractor, the Principal Designer must "plan, manage and monitor" part of the project delivery, namely the pre-construction phase.
The Principal Contractor (and even the Contractor for smaller less complex projects) must produce a Construction Phase Plan. This makes sense. In order "to plan" you need "a plan".
Since the Principal Designer has a similar duty, there is an implied requirement on the Principal Designer to produce a Design Management Plan, Design Execution Plan or Pre-Construction Phase Plan.
The list of headings provided here is helpful because it shows how to integrate H&S into projects rather than having it as a separate item.
Like many other aspects such as the commercial aspects, professionals need to be continuously mindful of the issues and occasional focussed on them.
Liz Bennett
[email protected]