Change control procedure for building design and construction
Changes to a project may have impacts on time, cost or quality. Broadly, the later in the development of the project that changes occur, the greater those impacts are likely to be.
At certain stages in the design process, a complete package of information will be provided for the client to approve. Once this approval has been given, a change control procedure may be introduced to ensure that the approved information is not changed without the express permission of the client.
The CIOB 'Code of practice for project management' (4th edition), defines change control as 'a process that ensures potential changes to the deliverables of a project or the sequence of work in a project, are recorded, evaluated, authorised and managed.'
Examples of stages where change control procedures might be introduced include:
- At the end of the concept design stage if the project is tendered at this stage (for example on a design and build project).
- At the end of the concept design stage when the project brief (and employer's information requirements) might be frozen.
- During the detailed design stage when the detailed design, technical design and specification are finalised.
- During the tender stage when the tender documentation has been prepared.
- When the contractor is appointed and any further changes may qualify as variations.
It is important that the need for changes is minimised. This can be done by:
- Undertaking thorough site investigations and condition surveys.
- Ensuring that the project brief is comprehensive and is supported by stakeholders.
- Ensuring that legislative requirements are properly integrated into the project.
- Ensuring that risks are properly identified.
- Ensuring that designs are properly co-ordinated before tender.
It is common for the cost consultant to report on the estimated cost of changes and for the client to prioritise which changes are acceptable. The client may decide to fund additional costs from a design contingency. A change control procedure should clearly define the process by which changes are requested and approved and who is responsible for those processes, including:
- The reasons for the change.
- Who is requesting the change.
- The consequences of the change, including health and safety, time, quality, cost (and who will bear the cost).
- Proposals for mitigation of any consequences.
- The risks associated with the change.
- Alternatives to the proposed change.
- Time by which the change must be instructed.
There may then be:
- Client evaluation of whether the impact of the change is acceptable and whether the proposal provides value for money.
- Client instructions to the consultant team.
- Contract administrator instructions to the contractor.
The client may have to consider a number of requests for changes and may therefore need the appropriate information to be able to prioritise them relative to one another.
Change control procedures should be formally set out in a project quality plan to ensure that changes to controlled aspects of the project are referred for review to the right person at the right time and so that changes are properly documented and reflected in all project information.
NB In the context of the UK Building Safety Act, a change control plan is a structured process and documentation system implemented to manage changes to a building's design, construction, or management that may impact its safety or compliance with building regulations. The change control plan outlines procedures for assessing proposed changes, determining their potential impact on building safety, and ensuring that appropriate measures are taken to maintain or enhance safety standards. By implementing a change control plan, building owners and managers can ensure that any modifications to a building are carefully assessed, managed, and implemented to maintain or improve safety standards and compliance with building regulations, as mandated by the Building Safety Act.
[edit] Related articles on Designing Buildings
- Abortive work.
- Change control: a quality perspective.
- Change management.
- Common data environment.
- Condition Report.
- Construction industry knowledge standard.
- Cost control.
- Design freeze.
- Design chill.
- Document control.
- End of stage report.
- Gateways.
- Henry Boot Construction Ltd v Alstom Combined Cycles.
- Project brief derogations.
- Milestones.
- Scope creep.
- Variation.
- Value engineering.
- Value management.
[edit] External references
- OGC guidance on managing changes to requirements.
- OGC Achieving Excellence Guide 3 - Project ProcurementLifecyclepage 21.
- RICS draft guidance note: Managing the design delivery (including an example project change notice).
Featured articles and news
CIAT Celebrates 60 years of Architectural Technology
Find out more #CIAT60 social media takeover.
The BPF urges Chancellor for additional BSR resources
To remove barriers and bottlenecks which delay projects.
Flexibility over requirements to boost apprentice numbers
English, maths and minimumun duration requirements reduced for a 10,000 gain.
A long term view on European heating markets
BSRIA HVAC 2032 Study.
Humidity resilience strategies for home design
Frequency of extreme humidity events is increasing.
National Apprenticeship Week 2025
Skills for life : 10-16 February
Update on the future of Grenfell Tower
Deputy Prime Minister decides for it be carefully taken down to the ground.
Ending decades of frustration, misinformation and distrust.
Essential tools in managing historically significant landscapes.
Classroom electrician courses a 'waste of money'
Say experts from the Electrical Contractors’ Association.
Wellbeing in Buildings TG 10/2025
BSRIA topic guide updates.
With brief background and WELL v2™.
From studies, to books to a new project, with founder Emma Walshaw.
Types of drawings for building design
Still one of the most popular articles the A-Z of drawings.
Who, or What Does the Building Safety Act Apply To?
From compliance to competence in brief.
The remarkable story of a Highland architect.
Commissioning Responsibilities Framework BG 88/2025
BSRIA guidance on establishing clear roles and responsibilities for commissioning tasks.
Comments
How do i cite this article
Have a look at this https://www.designingbuildings.co.uk/wiki/Citing_an_article_on_Designing_Buildings