Self-build home: project plan
This is a free-to-use, open-access plan for the organisation, design and construction of self-build homes.
If you have ideas for things to add to the plan, you can either edit the plan and add them yourself, or submit a comment and we will add them for you.
There are a number of delivery routes for self-build homes:
- Purchase a kit house.
- Appoint a design and build contractor to design and build the home.
- Appoint consultants to design the home then get a contractor to build it.
- Appoint consultants to design the home then manage the construction yourself.
It may not be clear which route should be followed until initial assessments have been carried out, a plot located and a brief prepared. See: Develop a delivery strategy for more information.
It is also possible to work with other organisations such as social landlords, developers, or community groups to develop a self-build home, however, these projects are likely to follow a plan imposed by the lead organisation and so they are not covered here, although many of the project stages will be similar. Working with a developer is sometimes called ‘custom build’ rather than ‘self build’.
See Custom-build home for more information.
An outline project plan is presented below. It describes activities step-by-step from the first moment it becomes apparent a self-build home could be a possibility right through to occupation of the completed building. Most of the stages are common to all four self-build routes, but the appointment stages vary.
Clicking on any of the stages will take you to a detailed description of the tasks that need to be carried out.
Stage 1: Justify the project.
Stage 2: Prepare a brief.
Stage 3: Find a plot.
Stage 4: Develop a delivery strategy.
Stage 5: Raise finance.
Stage 6: Acquire the plot.
Stage 7: Appoint designers.
- Appoint consultants to design the home, or;
- Appoint a contractor to design the home, or;
- Appoint a supplier to design a kit house.
Stage 8: Prepare a concept design.
Stage 9: Submit a planning application.
Stage 10: Prepare a detailed design.
Stage 11: Submit a building regulations application.
Stage 12: Prepare production information.
Stage 13: Appoint contractors.
- Appoint a contractor to construct the home, or;
- Appoint a range of contractors and suppliers to construct the home, or;
- Confirm appointment of the design and build contractor to construct the home, or;
- Confirm appointment of the supplier to fabricate and install the kit house.
Stage 14: Prepare for construction.
Stage 16: Construction.
Stage 17: Occupy the home and rectify any defects.
Featured articles and news
Not buildings. Happy holiday from DB.
Improving government projects with data and AI
Enabling better outcomes, efficient modern delivery and influential leadership on government projects.
BSRIA Living Laboratory Innovation Challenge
Final days for submission, closing March 29.
Windows, their frames, forms, factors and functions.
The hidden subtleties of U-Value calculations
Different contexts and what to include as variables.
A brief run down with related articles.
Electrical sector calls for safer public EV charge points
Serious concerns about electrical safety in the public domain.
Building Blocks manifesto presented to parliament
Architects Declare call in for support of five critical policies.
The four elements of project management with APM
Analysis, expectations, collaborative communication and partnerships.
City of London launches Heritage Building Retrofit Toolkit
Empowering owners to initiate necessary adaptations.
Guidance on RAAC in listed buildings
Published by Purcell, endorsed by IHBC, SPAB and C20.
Learning from the past.
Reluctance to hire people with criminal convictions revealed
Employing People with Criminal Convictions Report.
Tackling unconscious bias; Women's History Month
Personal reflections, as the last week of March approaches.
Comments
It seems that the handover information such as building manual, H&S files, and other operation and maintenance documents are not mentioned here.
Not surpised that most building owners do not know what is in their building.