Time of the essence in construction contracts
The term ‘Time is of the essence’ refers to a contractual position in which, if one of the parties to the contract fails to complete their obligations by a specified date, then the other party can treat the contract as terminated. This might be appropriate for example in the supply of perishable goods where late delivery would go to the ‘root’ of the contract, depriving the innocent party of the whole benefit of the contract. They may then terminate the contract and claim damages.
Time can be of the essence if the contract says it is, or where it can be implied from the contract. Setting a completion date is not sufficient to make time of the essence. However, where one party has caused delay, the other party can give notice requiring completion by a certain date, thereby making time of the essence.
Typically on construction contracts, time is not of the essence, but rather a completion date is set (the date by which practical completion must be certified). There are generally mechanisms allowing the completion date to be adjusted, and liquidated damages can be claimed by the client if delays that are the fault of the contractor result in a failure to complete the works by the completion date. However, the contract is not terminated, and to do so would generally not be in the interests of either party.
If ‘time is at large’, ie there is no date for completion, or the date for completion has become invalid (with no mechanism for extension), then the contractor is no longer bound by the obligation to complete the works by a certain date. The client would then not be able to claim liquidated damages from the contractor and the contractor would only have to complete the works in a 'reasonable' time. The client would then only be entitled to damages if they could established that the contract was not completed within a reasonable time.
Whilst time is generally not of the essence in construction contracts, they do tend to include a requirement that the contractor proceeds ‘regularly and diligently’ irrespective of whether it is apparent that the completion date will be achieved.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
ECA 2024 Apprentice of the Year Award
Entries open for submission until May 31.
UK gov apprenticeship funding from April 2024
Brief summary the policy paper updated in March.
For the World Autism Awareness Month of April.
70+ experts appointed to public sector fire safety framework
The Fire Safety (FS2) Framework from LHC Procurement.
Project and programme management codes of practice
CIOB publications for built environment professionals.
The ECA Industry Awards 2024 now open !
Recognising the best in the electrotechnical industry.
Sustainable development concepts decade by decade.
The regenerative structural engineer
A call for design that will repair the natural world.
Buildings that mimic the restorative aspects found in nature.
CIAT publishes Principal Designer Competency Framework
For those considering applying for registration as a PD.
BSRIA Building Reg's guidance: The second staircase
An overview focusing on aspects which most affect the building services industry.
Design codes and pattern books
Harmonious proportions and golden sections.
Introducing or next Guest Editor Arun Baybars
Practising architect and design panel review member.
Quick summary by size, shape, test, material, use or bonding..
Comments
To start a discussion about this article, click 'Add a comment' above and add your thoughts to this discussion page.