Third party dependencies for building design and construction
Not every aspect of a project is within the direct control of the client or their project team. Every project is dependent to some extent on third parties. It is important that these third party dependencies are identified and that their potential impacts are understood, quantified and managed.
Third parties may not be motivated by the same objectives as the client or project team, but nevertheless they can have a serious impact on the programme for a project. It is not safe to assume, just because a time allocation has been made within a programme for a third party dependency, that the third party has any interest in keeping to that programme.
These third parties are often different from stakeholders in that they may have no interest in the project or any ability to affect decisions, and yet they may still be in a position to impact upon success.
Third parties can even be responsible for completely unrelated, circumstantial dependencies, such as the legislative framework. For example, the introduction of changes to the building regulations can have a very significant impact on a project and yet are entirely beyond the control of the project team.
The range of potential third party dependencies is very wide and will vary from project to project, but may include:
- Neighbours (planning matters, party wall matters, access and other permissions, easements, right to light, tree rights and so on).
- Licensing authorities.
- Planning authorities.
- Building control.
- Other statutory authorities and non-statutory authorities (Health and Safety Executive, Environment Agency, Civil Aviation Authority, English Nature, Historic England, CABE, Highways England and so on – see Statutory authorities for more information).
- Utilities companies and other statutory undertakers.
- Purchasers or vendors of land or properties.
- Archaeological or other surveyors (surveys can reveal issues such as; archaeological remains, unexploded bombs, asbestos, contamination, japanese knotweed, roosting bats, great crested newts, tree preservation orders and so on that can cause very significant delays to a project).
- Dependent projects (for example decontamination of the site by a third party prior to sale of land to the client).
- Funding availability.
- Local Chambers of Commerce.
- Politicians.
- Competitors.
- The supply market (goods, labour, plant, equipment and so on).
- Unions.
- The availability of third party services (such as local schools, feeder organisatons, local transport, local infrastructure and so on.)
- The political and legislative framework.
- The wider economic context.
- Customers.
- Emergency services.
- Community groups.
- Special interest groups.
- The press.
Identifying and assessing these third party dependencies should involve the whole project team, and can be best carried out at a project workshop (for example it may form part of a risk workshop – see risk register for more information). Techniques such as PEST analysis (Political, Economic, Social, Technological) can help identify third party dependencies.
It is important that this is not simply a paper exercise. The probability and importance of impacts should be assessed so that resources can be prioritised, responsibilities allocated and strategies put in place to monitor progress (see stakeholder and stakeholder map for more information about how this might be done).
Where risks remain, strategies should be put in place to mitigate, transfer, avoid or accept those risks. See risk register for more information.
[edit] Related articles on Designing Buildings Wiki
- BREEAM independent party.
- Collaborative practices.
- Consultation process.
- Dependency.
- Early BREEAM stakeholder engagement.
- Externalities.
- Independent third party.
- Interested party.
- Receptor.
- Risk management.
- Risk register.
- Stakeholders.
- Stakeholder management: a quality perspective.
- Stakeholder map.
- Statutory authorities.
- Statutory undertakers.
- Technical due diligence.
- Utilities.
Featured articles and news
Not buildings. Happy holiday from DB.
Future Homes Standard: Industry calls for more ambition
As the Government FHS consultation finally closes.
Improving government projects with data and AI
Enabling better outcomes, efficient modern delivery and influential leadership on government projects.
BSRIA Living Laboratory Innovation Challenge
Final days for submission, closing March 29.
Windows, their frames, forms, factors and functions.
The hidden subtleties of U-Value calculations
Different contexts and what to include as variables.
A brief run down with related articles.
Electrical sector calls for safer public EV charge points
Serious concerns about electrical safety in the public domain.
Building Blocks manifesto presented to parliament
Architects Declare call in for support of five critical policies.
The four elements of project management with APM
Analysis, expectations, collaborative communication and partnerships.
City of London launches Heritage Building Retrofit Toolkit
Empowering owners to initiate necessary adaptations.
Guidance on RAAC in listed buildings
Published by Purcell, endorsed by IHBC, SPAB and C20.
Learning from the past.
Reluctance to hire people with criminal convictions revealed
Employing People with Criminal Convictions Report.
Tackling unconscious bias; Women's History Month
Personal reflections, as the last week of March approaches.
Comments
To start a discussion about this article, click 'Add a comment' above and add your thoughts to this discussion page.