Target cost for construction
Target costs are generally associated with cost-reimbursable contracts. They introduce a mechanism enabling the contractor, and sometimes the consultant team, to share in the benefits of cost savings, but also to bear some of the client's cost when there are cost overruns. Contracting the contractor and the consultant team on a target cost basis can be an effective way of ensuring good collaboration.
The target cost is set early in the project, and then cost savings or overruns are shared based on an agreed formula. The aim is to provide a financial incentive encouraging cost control, rather than to penalise. Bonus and penalty payments are usually capped to prevent over-zealous or adversarial behaviour.
Target costs might be set for the overall project, or for specific elements of the works. Agreeing the target cost requires that the client has sufficient knowledge and experience to be able to accurately estimate the likely cost of the works and to negotiate effectively with the contractor and sometimes the consultant team.
Examples of target cost contracts include the New Engineering Contract (NEC) Engineering and Construction Contracts Option C: Target contract with activity schedule and Option D: Target contract with bill of quantities.
NB: According to NRM2: Detailed measurement for building works, in the context of bills of quantities, the term ‘cost target' means; '...the total expenditure for an element or
work package.'
[edit] Related articles on Designing Buildings
- Bill of quantities.
- Construction contract.
- Contract condition.
- Contract sum.
- Cost overruns.
- Cost-reimbursable contract.
- Disallowed cost.
- Fast-track construction.
- Fixed price contract.
- Force account work.
- Guaranteed maximum price.
- Lump sum contract - pros and cons.
- New Engineering Contract.
- Open-book accounting.
- Procurement route.
- Target contract.
[edit] External references
Featured articles and news
Introducing or next Guest Editor Arun Baybars
Practising architect and design panel review member.
Quick summary by size, shape, test, material, use or bonding.
Types of rapidly renewable content
From forestry to agricultural crops and their by-products.
Terraced houses and the public realm
The discernible difference between the public realm of detached housing and of terraced housing.
Put digitalisation and sustainability at the core of curricula
Project management educators are urged.
Looking back at the influence of climate events
From a designer and writer: 'There are limits to growth but no limits to development'.
Terms, histories, theories and practice.
Biophilic design and natural light
Letting in the light and natural elements into spaces.
APM Programme Management Conference 2024
Strategies for Success.
Residential takes the reins as contract awards even out
Contracts down, but remain above the last quarter of 2023.
Celebrating Eid and the largest mud-brick building.
Barry Kingscote claims prestigious CIOB CMYA Award.
The British Mosque: an architectural and social history
The story of some 1,500 mosques or more in Britain.
Heat pump refrigerants, efficiencies and impacts
R12 to R1270 what are the differences?
Global heat pump market in 2023
Challenging times with positive but modest outlook.
Beyond the infrastructure pipeline
Opportunities and chokepoints.