Negotiated contract
In order to procure a building, a client will normally have to appoint a number of suppliers. There are a number of procedures that can be adopted to select and appoint suppliers.
- Open procedures.
- Selective procedures.
- Negotiated procedures.
- Serial procedures.
- Framework procedures.
Each has its own advantages and disadvantages which must be considered in relation to the particular objectives and scope of the project.
Some of these procedures involve competitive bidding between multiple contractors, whereas the negotiated procedure involves negotiations with just one pre-selected contractor.
In competitive bidding, a contract is agreed following a tendering process where the award is often made to the cheapest (or best value) tender. The concept of negotiation generally allows more flexibility for the client to select a contractor on a basis other than the lowest bid. Negotiated contracts are generally agreed between a contractor and client that have experience of working together and have a relationship built on trust.
Negotiating with a single supplier may be particularly appropriate for highly-specialist works where there may only be a limited number of potential suppliers, or for extending the scope of an existing contract. It can give the client the confidence of working with a supplier they already know, can reduce the duration and costs of tendering and can allow early supplier involvement.
As the design documents very often have not been completed at the negotiation stage, a cost plus contract or cost reimbursable contract is commonly used for negotiated tenders. This allows for the reimbursement of the contractor for the costs incurred during construction, such as labour, equipment and materials, as well as profit and overhead charges for the management of the project.
However, despite having the advantage of being more flexible, negotiated contracts can also be less attractive for clients who may see the lack of competitive tendering as driving up costs; though it is often the case that a strong working relationship with a contractor whose practice is well-known may more than make up for this over the duration of the project.
Negotiated contracts may not be permitted by some organisations due to the perceived lack of accountability. On public projects, or projects that include a publicly-funded element it may be necessary to advertise contracts.
Advantages:
- Client has flexibility in terms of choosing their preferred contractor.
- Time and cost savings involved in removing the tendering process.
- It can allow early supplier involvement.
- Contractor’s costs and pricing are more transparent as they are not seeking to win the bid purely on the lowest tender.
Disadvantages:
- There are fewer options for the client to choose between and so there may be less innovation.
- The costs may be driven up by the lack of competitive bidding.
- There is a heavy reliance on trust between the parties.
- Unless it is carefully structured and controlled, the negotiation process can create an adversarial atmosphere, even before the contract has been awarded.
- It can be seen as anti-competitive and exclusive, with the potential for ‘cozy’ relationships to develop between the client and the supplier.
[edit] Related articles on Designing Buildings Wiki:
- Back to back provisions in construction contracts.
- Competitive procedure with negotiation.
- Construction contract.
- Contract award.
- Contract negotiation.
- Contract strategy.
- Contractual documents.
- Cost plans.
- Design and build procurement route.
- Essentials of a contract.
- Fixed price construction contract.
- Form of tender.
- Major project construction contract.
- Negotiated Procedure without Prior Publication NPwPP.
- Negotiation techniques.
- Performance specification.
- Tender evaluation.
- Sub-contract.
- Whole-life costs.
[edit] External references
- Construction Management (4th ed.), HALPIN, D.W., SENIOR, B.A., Wiley, (2011)
Featured articles and news
Introducing or next Guest Editor Arun Baybars
Practising architect and design panel review member.
Quick summary by size, shape, test, material, use or bonding.
Types of rapidly renewable content
From forestry to agricultural crops and their by-products.
Terraced houses and the public realm
The discernible difference between the public realm of detached housing and of terraced housing.
Put digitalisation and sustainability at the core of curricula
Project management educators are urged.
Looking back at the influence of climate events
From a designer and writer: 'There are limits to growth but no limits to development'.
Terms, histories, theories and practice.
Biophilic design and natural light
Letting in the light and natural elements into spaces.
APM Programme Management Conference 2024
Strategies for Success.
Residential takes the reins as contract awards even out
Contracts down, but remain above the last quarter of 2023.
Celebrating Eid and the largest mud-brick building.
Barry Kingscote claims prestigious CIOB CMYA Award.
The British Mosque: an architectural and social history
The story of some 1,500 mosques or more in Britain.
Heat pump refrigerants, efficiencies and impacts
R12 to R1270 what are the differences?
Global heat pump market in 2023
Challenging times with positive but modest outlook.
Beyond the infrastructure pipeline
Opportunities and chokepoints.