Last edited 03 Feb 2016

Fixed price construction contract

Lump sum (or stipulated sum) contracts are sometimes referred to as ‘fixed price’ contracts, although strictly this is not correct.

On a lump sum contract, a single ‘lump sum’ price is agreed before the works begin. If the actual cost of the works exceeds the agreed price, then the contractor must bear the additional expense. If on the other hand the cost of the works is less than the agreed price, the contractor will benefit from the savings.

This is unlike a guaranteed maximum price contract, where the contractor bears any additional costs above the guaranteed maximum price, but if the cost is lower than the guaranteed maximum price, then savings may go to the client, to the contractor or are shared. An extension of this is the target cost contract, where there is a ‘pain / gain’ agreement allowing the client and contractor to share both additional costs and savings.

However, lump sum contracts tend not to be fixed, but allow the price to change under certain circumstances:

A truly 'fixed' price contract would not necessarily be in the interests of the client as it would require that the contractor price risks over which they may have no control, and which might not arise.

[edit] Find out more

[edit] Related articles on Designing Buildings Wiki