Defined cost
A cost reimbursable contract (sometimes called a cost plus contract) is one in which the contractor is reimbursed the actual costs they incur in carrying out the works, plus an additional fee.
Their actual costs are calculated based on their accounts and records, rather than a pre-determined rate or price. However, not all costs can be accurately determined on a project-specific basis, some costs have only been incurred due to the contractor’s inefficiency, and not all costs are recoverable under the contract.
Options (C, D, E and F) of the NEC (New Engineering Contract), EEC contract (Engineering and Construction Contract), describe the costs that can be recovered by the contractor as the ‘defined cost’, whereas the costs that cannot be recovered are described as the ‘disallowed cost’.
Very broadly, the defined cost includes payments due to subcontractors and the cost of components for other works (such as plant, equipment, people and so on), minus the disallowed cost.
The contract stipulates that only amounts incurred to provide the works are recoverable as cost components. If an amount can be classified as one component, such as ‘equipment’, then it cannot also fall within another, such as ‘people’.
There are seven cost component criteria:
- People: Those directly employed or paid by the contractor to carry out the works.
- Equipment: Items provided by the contractor and used to provide the works.
- Plant and materials: Items intended to be used and included in the works.
- Charges: Cancellation charges arising from a compensation event, payment to public authorities, specialist services, and so on.
- Manufacture and design: Only apply if they are outside the working areas and wholly or partly designed specifically for the works.
- Design: Costs for the works and equipment only.
- Insurance: Does not actually facilitate cost recovery for the contractor. Costs that would otherwise be recoverable that have been paid by the insurer to the contractor are set off against the recoverable cost.
[edit] Related articles on Designing Buildings Wiki:
- Articles of agreement.
- Cost reimbursable contract.
- Delay damages.
- Disallowed cost.
- Latham Report.
- NEC3.
- NEC contract change management systems.
- NEC early contractor involvement.
- Right to payment.
- Variations.
- Works information.
- Z clauses.
[edit] External references
Featured articles and news
Introducing or next Guest Editor Arun Baybars
Practising architect and design panel review member.
Quick summary by size, shape, test, material, use or bonding.
Types of rapidly renewable content
From forestry to agricultural crops and their by-products.
Terraced houses and the public realm
The discernible difference between the public realm of detached housing and of terraced housing.
Put digitalisation and sustainability at the core of curricula
Project management educators are urged.
Looking back at the influence of climate events
From a designer and writer: 'There are limits to growth but no limits to development'.
Terms, histories, theories and practice.
Biophilic design and natural light
Letting in the light and natural elements into spaces.
APM Programme Management Conference 2024
Strategies for Success.
Residential takes the reins as contract awards even out
Contracts down, but remain above the last quarter of 2023.
Celebrating Eid and the largest mud-brick building.
Barry Kingscote claims prestigious CIOB CMYA Award.
The British Mosque: an architectural and social history
The story of some 1,500 mosques or more in Britain.
Heat pump refrigerants, efficiencies and impacts
R12 to R1270 what are the differences?
Global heat pump market in 2023
Challenging times with positive but modest outlook.
Beyond the infrastructure pipeline
Opportunities and chokepoints.