Deferment of possession
Contracts generally grant the contractor exclusive possession of the site until practical completion when a handover meeting takes place and possession reverts to the client (see handover to client). The contract may state the date for possession of the site by the contractor (sometimes called the 'commencement date'), or, if not, then the site must be handed over to the contractor within a reasonable time after signing of the contract.
Some contracts (such as the JCT Standard Form of Building Contract) will entitle the client to defer giving the contractor possession of the site for a period of up to six weeks unless a shorter period was stipulated in the contract particulars (it is probably unwise to reduce the period). This provision enables the client to defer possession without being in breach of contract.
It is considered that deferment of possession is a positive activity which the employer should signal by giving written notice although that is not expressly stated.
Deferment of possession can be considered a relevant matter, giving rise to the possibility of the contractor claiming an extension of time or loss and expense. However, for such a claim to succeed, the deferment must have a material effect on the regular progress of the works. Obviously, deferment will have an immediate effect on progress, however, it does not extend the contract period, it simply moves it in time with dates for possession and completion which continue to have the same relationship to each other.
If the contractor is given early notice of deferment, they are likely to incur far fewer costs than if the deferment is only notified a few days before start on site. Issues that might be considered include:
- Plant hire.
- The possibility of using operatives elsewhere.
- Delivery dates
- Key dates for sub-contractors
- The possibility of increased costs and interest charges.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Introducing or next Guest Editor Arun Baybars
Practising architect and design panel review member.
Quick summary by size, shape, test, material, use or bonding.
Types of rapidly renewable content
From forestry to agricultural crops and their by-products.
Terraced houses and the public realm
The discernible difference between the public realm of detached housing and of terraced housing.
Put digitalisation and sustainability at the core of curricula
Project management educators are urged.
Looking back at the influence of climate events
From a designer and writer: 'There are limits to growth but no limits to development'.
Terms, histories, theories and practice.
Biophilic design and natural light
Letting in the light and natural elements into spaces.
APM Programme Management Conference 2024
Strategies for Success.
Residential takes the reins as contract awards even out
Contracts down, but remain above the last quarter of 2023.
Celebrating Eid and the largest mud-brick building.
Barry Kingscote claims prestigious CIOB CMYA Award.
The British Mosque: an architectural and social history
The story of some 1,500 mosques or more in Britain.
Heat pump refrigerants, efficiencies and impacts
R12 to R1270 what are the differences?
Global heat pump market in 2023
Challenging times with positive but modest outlook.
Beyond the infrastructure pipeline
Opportunities and chokepoints.