Contractual documents
This article lists the documents that are commonly required by or referred to in a construction contract. See also Contract documents for a list of the documents setting out the obligations and responsibilities of the parties to the contract on a traditionally-procured, fully-designed construction project,
In some cases, different contracts may use different names for the same document. Where this is the case, alternative names are shown.
- Application for payment (see Fair payment practices)
- Architect's instruction / contract administrator's instruction
- Bill of quantities
- Building log book
- Building owner's manual / operation and maintenance manual (O&M manual)
- Building users guide
- Certificate of making good defects / certificate of making good
- Collateral warranty
- Construction phase plan
- Contract sum analysis
- Contractors master programme
- Contractors proposals
- Default payment notice (see Fair payment practices)
- Contract drawings
- Design documents
- Employers requirements
- Final account
- Final certificate
- Health and safety file
- Information release schedule
- Insurance
- Interim certificate
- Joint fire code
- Method statement
- Pay less notice (see Fair payment practices)
- Payment notice (see Fair payment practices)
- Practical completion certificate / substantial completion certificate
- Preliminaries
- Risk assessment
- Schedule of defects
- Schedule of work
- Site waste management plan
- Specification
NB: A pre-contract meeting is likely to take place after the contractor has been appointed but before work commences on site. This is an opportunity to for the project team to meet (perhaps for the first time) and to plan the construction stage. The minutes of the pre-contract meeting may form part of contract documents (for all procurement routes) subject to the agreement of both parties.
See Pre-contract meeting for more information.
[edit] Related articles on Designing Buildings Wiki
- Bills of quantities.
- Construction contract.
- Contract conditions.
- Contract documents.
- Contractors proposals.
- Contract sum analysis.
- Employers requirements.
- Form of tender.
- Information release schedule.
- Performance bond.
- Pre-contract meeting.
- Procurement route.
- Schedules of work.
- Specifications.
- Tender.
- Tender documents.
Featured articles and news
For the World Autism Awareness Month of April.
70+ experts appointed to public sector fire safety framework
The Fire Safety (FS2) Framework from LHC Procurement.
Project and programme management codes of practice
CIOB publications for built environment professionals.
Sustainable development concepts decade by decade.
The regenerative structural engineer
A call for design that will repair the natural world.
Buildings that mimic the restorative aspects found in nature.
CIAT publishes Principal Designer Competency Framework
For those considering applying for registration as a PD.
BSRIA Building Reg's guidance: The second staircase
An overview focusing on aspects which most affect the building services industry.
Design codes and pattern books
Harmonious proportions and golden sections.
Introducing or next Guest Editor Arun Baybars
Practising architect and design panel review member.
Quick summary by size, shape, test, material, use or bonding.
Types of rapidly renewable content
From forestry to agricultural crops and their by-products.
Terraced houses and the public realm
The discernible difference between the public realm of detached housing and of terraced housing.