Contingency plan
Contingency plans are plans than could be enacted to mitigate project risks identified during risk assessment, if those risks increase or materialise. That is, they are alternative courses of action devised to cope with project risks.
Predictable risks that could be mitigated with forward planning might include:
- Non-delivery of materials. An alternative design might be prepared, or bulk or specific items could be pre-ordered before contractors are appointed
- Lack of available work force. This could be tackled by the provision of a site labour camp or by overseas recruitment.
- Lack of plant and equipment availability (or plant failure or access to spare parts). Plant such as piling rigs and spares could be ordered during the design stages prior to contractor involvement.
- Illness. This could be mitigated by insurance cover for key personnel.
- The risk of obtaining planning permission or other statutory approvals. This might be mitigated by early consultation with statutory authorities prior to design, or by employing ex-statutory authority employees, or consultants familiar with the statutory authority.
- Information and communications technology failure. This might be mitigated by duplicating facilities, establishing back-up procedures and providing uninterrupted power supplies.
- Failure of power or water supply. This might be mitigated by the duplication of supply, uninterrupted power supplies or the provision of standby generators.
NB Functional Standards Common Glossary, published by the Cabinet Office, defines contingency planning/ plans as: ‘A course of action and resulting document(s) that prepares the organisation to respond effectively to future significant events, incidents and risks.’
[edit] Related articles on Designing Buildings
Featured articles and news
Not buildings. Happy holiday from DB.
Future Homes Standard: Industry calls for more ambition
As the Government FHS consultation finally closes.
Improving government projects with data and AI
Enabling better outcomes, efficient modern delivery and influential leadership on government projects.
BSRIA Living Laboratory Innovation Challenge
Final days for submission, closing March 29.
Windows, their frames, forms, factors and functions.
The hidden subtleties of U-Value calculations
Different contexts and what to include as variables.
A brief run down with related articles.
Electrical sector calls for safer public EV charge points
Serious concerns about electrical safety in the public domain.
Building Blocks manifesto presented to parliament
Architects Declare call in for support of five critical policies.
The four elements of project management with APM
Analysis, expectations, collaborative communication and partnerships.
City of London launches Heritage Building Retrofit Toolkit
Empowering owners to initiate necessary adaptations.
Guidance on RAAC in listed buildings
Published by Purcell, endorsed by IHBC, SPAB and C20.
Learning from the past.
Reluctance to hire people with criminal convictions revealed
Employing People with Criminal Convictions Report.
Tackling unconscious bias; Women's History Month
Personal reflections, as the last week of March approaches.
Comments
[edit] To make a comment about this article, or to suggest changes, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.