Construction progress report
Construction progress reports are prepared regularly (often monthly) by the contract administrator during the construction phase and issued to the client. They will generally be a summary of the reports received and discussions held at construction progress meetings.
Construction progress reports may be a combination of minutes of construction progress meetings and reports received during those meetings, with key issues highlighted in an accompanying cover note. Alternatively they may be a re-written version of that information prepared specifically to suit the client's requirements.
Construction progress reports might include:
- A summary of the progress made in each key area of the project.
- Analysis of progress against the programme
- An explanation of the causes of any delays.
- Progress photos.
- Analysis of key performance indicators.
- An assessment of any quality issues.
- Weather reports.
- An assessment of any health and safety issues.
- Reports of any issues with neighbours (such as noise, dust, vibrations, rights of light, access, safety etc).
- Reports about off-site fabrication and off-site payments.
- Earned value analysis.
- An assessment of any design issues.
- An assessment of any other issues that need to be addressed and proposals for addressing them.
- Any instructions required from the client.
- Look ahead to the next period (including specific requirements for progress photos during the next period, which may include off-site fabrication photos).
On construction management projects, the construction manager holds regular construction progress meetings with the client and consultant team, however they will also hold regular construction progress meetings with trade contractors to discuss on and off-site progress against the programme and to co-ordinate the release of information. It may sometimes be appropriate for these meetings to take place at the trade contractor's premises. Construction progress reports will then be prepared for the client.
Similar reports may be prepared on management contract projects in relation to works contractor progress.
[edit] Related articles on Designing Buildings Wiki
- Client.
- Construction progress meeting.
- Construction manager.
- Contractor.
- Contract administrator.
- Consultant team.
- Construction stage report.
- Earned value analysis.
- Employer's agent.
- Health and Safety.
- Management contractor.
- Progress of construction works.
- Project programme.
- Project manager.
- Project manager's report.
- Site meeting.
- Sub contractor.
- Warranties.
- Works contractor
Featured articles and news
Introducing or next Guest Editor Arun Baybars
Practising architect and design panel review member.
Quick summary by size, shape, test, material, use or bonding.
Types of rapidly renewable content
From forestry to agricultural crops and their by-products.
Terraced houses and the public realm
The discernible difference between the public realm of detached housing and of terraced housing.
Put digitalisation and sustainability at the core of curricula
Project management educators are urged.
Looking back at the influence of climate events
From a designer and writer: 'There are limits to growth but no limits to development'.
Terms, histories, theories and practice.
Biophilic design and natural light
Letting in the light and natural elements into spaces.
APM Programme Management Conference 2024
Strategies for Success.
Residential takes the reins as contract awards even out
Contracts down, but remain above the last quarter of 2023.
Celebrating Eid and the largest mud-brick building.
Barry Kingscote claims prestigious CIOB CMYA Award.
The British Mosque: an architectural and social history
The story of some 1,500 mosques or more in Britain.
Heat pump refrigerants, efficiencies and impacts
R12 to R1270 what are the differences?
Global heat pump market in 2023
Challenging times with positive but modest outlook.
Beyond the infrastructure pipeline
Opportunities and chokepoints.
Comments