Building owner's manual - O and M manual
The building owner's manual, or operation and maintenance manual (O&M manual), contains the information required for the operation, maintenance, decommissioning and demolition of a building.
The building owner's manual is prepared by the contractor or the sub-contractor with additional information from the designers (in particular, the services engineer) and suppliers. It is a requirement that is generally defined in the preliminaries section of the tender documentation where its contents will be described, although there may be additional requirements regarding mechanical and electrical services in the mechanical and electrical specification.
A draft version of the document should be provided for the client as part of the handover procedure prior to certifying practical completion. The final document is not usually available in full form until several months after practical completion, as commissioning information often needs to include summer and winter readings taken in the fully occupied building. The preliminaries may require several copies of the building owner's manual and might require an electronic version.
The building owner's manual might include:
- A description of the main design principles.
- Details of the building's construction (such as finishes, cladding, doors and windows, roof construction, and so on).
- As-built drawings and specifications.
- Instructions for its operation and maintenance (including health and safety information and manufacturers' instructions for efficient and proper operation).
- An asset register of plant and equipment.
- Commissioning and testing results.
- Guarantees, warranties and certificates.
- Particular requirements for demolition, decommissioning and disposal.
Much of this information will already exist in one form or another, so preparing the building owner's manual might simply be a matter of compiling and assembling its components.
Over the life of the buildings, the building owner's manual may be developed to reflect changes that take place to the fabric of the building or its systems, along with details of maintenance that has taken place .
The building owner's manual is different from the health and safety file which only needs to include information important to health and safety and does not need to include information about the construction process, contractual information or information about the normal operation of the completed structure.
The building owner's manual may also include a non-technical 'building user's guide' with information for users about environmental controls, access, security and safety systems, etc.
NB - Building owner's manuals might now be referred to as building manuals. For more information see: Building manual.
[edit] Related articles on Designing Buildings Wiki
- BSRIA updates Handover and O&M manuals.
- Building log book.
- Building manual.
- Building user's guide.
- Decommissioning.
- Deferred maintenance.
- End-user.
- Handover to client.
- Health and safety file.
- Maintenance.
- Operation, maintenance and training (OMT).
- Practical completion.
- Preliminaries.
- Soft Landings for owners.
- Technical guide.
- Tender documentation.
- Users.
- Working with maintenance contractors.
[edit] External references
- BSRIA Handover, O&M Manuals, and Project Feedback. A toolkit for designers and contractors (BG 1/2007).
Featured articles and news
A transformative shift in the design, construction and management of built assets.
Apprenticeship announcement by the Prime Minister
Welcomed but with call for more actionable detail.
Heat pump announcements, what homeowners need to know
An 'ultimate guide to heat pumps' from a heating company.
Construction contract awards reach 7.1bn in February
Their highest level in seven months.
The journey to sustainability in heritage
Research is the key to better understanding.
Heritage approaches to adaptation, mitigation and loss.
Bridging the gap between policy, finance and installation.
Development on brownfield land
Definition, background, policy and the latest consultation.
With the Design Framework for Building Services.
Retrofit of Buildings, a CIOB Technical Publication
Pertinent technical issues, measures and the roles involved.
ECA joins HSE campaign to support mental health
Working Minds’ five simple steps based on risk assessment.
Mental health in the construction industry
Mental health issues in brief with related articles.
Transitional arrangements, Building Control and the BSR.
For pre-October buildings with substantial progress by April.
Why quality counts in domestic ventilation systems
From products, to systems to the installation.
Empowering the Future with CIOB Academy
Lifelong learning, upscaling, and reskilling for the built environment.
Comments