Sectional completion in construction contracts
Hi
I note sectional completion may not include the completed M&E or other element etc depending on how it is detailed in the contract docs.
What about partial possession (which I know is not preplanned) . Can partial possession cert be issued of there are still outstanding issues such as M&E, fire alarm etc.
Presumably not because it has to be complete ?
Niall
Question
what are the item we need to compile in sectional completion?
how was the
format of sectional completion?
how to describe it is sectional completion
when we want to give them it is sectional completion? or how to make sectional
completion certificate? is it like handover? do we need to produce as built
drawing as per hand over?
Answer --designing buildings 08:19, 30 June 2013 (BST)
- All the things you need to do for completion apply to sectional completion (while listing any outstanding work such as commissioning and O and M manuals and as built drawings which embrace all sections).
- Sectional completion requirements must be either stipulated in tender documentation or be agreed by both parties and incorporated as an instruction.
- It requires a certificate and sets out the percentage release of retention. In effect it follows normal handover procedures but applicable to a defined area. It normally excludes mechanical and electrical
- service systems which are reliant on total completion before they can be properly tested and commissioned.
- This means that their needs to be an agreed protocol for re-entry into handed over areas for the contractors to complete outstanding work.
- Insurance provisions as well as security and access are issues of responsibility that should be addressed prior to granting sectional completion.
This project is under construction. Certain section is completed. Can we make sectional completion even there is not stated sectional completion in the document contract. Does it wrong contractually?
Sectional completion is agreed before the contract is entered into. Partial possession or early use can be agreed whilst the contract is running.
You must sign in or register to edit or comment on an article
Return to Talk:Sectional completion in construction contracts.
Featured articles and news
Not buildings. Happy holiday from DB.
Future Homes Standard: Industry calls for more ambition
As the Government FHS consultation finally closes.
Improving government projects with data and AI
Enabling better outcomes, efficient modern delivery and influential leadership on government projects.
BSRIA Living Laboratory Innovation Challenge
Final days for submission, closing March 29.
Windows, their frames, forms, factors and functions.
The hidden subtleties of U-Value calculations
Different contexts and what to include as variables.
A brief run down with related articles.
Electrical sector calls for safer public EV charge points
Serious concerns about electrical safety in the public domain.
Building Blocks manifesto presented to parliament
Architects Declare call in for support of five critical policies.
The four elements of project management with APM
Analysis, expectations, collaborative communication and partnerships.
City of London launches Heritage Building Retrofit Toolkit
Empowering owners to initiate necessary adaptations.
Guidance on RAAC in listed buildings
Published by Purcell, endorsed by IHBC, SPAB and C20.
Learning from the past.
Reluctance to hire people with criminal convictions revealed
Employing People with Criminal Convictions Report.
Tackling unconscious bias; Women's History Month
Personal reflections, as the last week of March approaches.